4423 W PROSPECT AVE 90027

Certificate Information: 4423 W PROSPECT AVE 90027

Application / Permit
19014-20000-02253
Plan Check / Job No.
B19VN07076
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR 11'-8" X 28'-0" AT FIRST FLOOR FOR NEW BEDROOM/BATHROOM/STAIRS; ADD IRREGULAR 12'-0" X 28'-0" AND 25'-6" X 27'-0" AT SECOND FLOOR FOR NEW BEDROOM/BATHROOMS/FAMILY ROOM FOR AN (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2019 APPLICANT
Green Plans Picked Up 5/10/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 JENNIFER LEE
Corrections Issued 5/22/2019 JENNIFER LEE
Quality Review Completed 5/22/2019 STEVEN KIM
Building Plans Picked Up 5/23/2019 APPLICANT
Plan Check Approved 9/26/2019 JENNIFER LEE
Issued 10/29/2019 LADBS
CofO in Progress 7/13/2022 ALIZAH MAYAGOITIA
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/25/2019 GUILLERMO PETRA
Sewer availability Cleared 7/25/2019 GUILLERMO PETRA
Project located in CRA area Cleared 8/2/2019 JIM URQUHART
Green Code Cleared 8/22/2019 COLIN LOREDO
GPI Written Notices Cleared 9/9/2019 JENNIFER LEE
Grading Pre-Inspection Cleared 9/9/2019 JENNIFER LEE
Low Impact Development Cleared 9/13/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/26/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 5/27/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 6/5/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 6/16/2020 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 6/26/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 6/26/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/31/2020 Partial Approval JOSEPH MCGARRY
Gas Test 7/31/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 7/31/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/6/2020 Partial Approval JOSEPH MCGARRY
Insulation 8/6/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Partial Approval JOSEPH MCGARRY
Special/Order Compliance 12/22/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 6/16/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 6/16/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/13/2021 Conditional Approval JOSEPH MCGARRY
Green Building Rough 7/13/2021 Approved JOSEPH MCGARRY
HVAC-Rough 7/13/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 7/13/2021 Corrections Issued JOSEPH MCGARRY
Shower Pan 7/13/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/28/2021 Approved JOSEPH MCGARRY
Insulation 7/28/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 7/28/2021 Approved JOSEPH MCGARRY
Drywall Nailing 8/12/2021 Approved CHARLES BOGHOSKHAN
Gas Test 8/12/2021 Approved CHARLES BOGHOSKHAN
Final 4/22/2022 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 4/22/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 4/22/2022 Corrections Issued ALIZAH MAYAGOITIA
Final 7/1/2022 Corrections Issued SHAVONNE ESPINOZA
Smoke Detectors 7/1/2022 Partial Inspection SHAVONNE ESPINOZA
Final 7/13/2022 OK to Issue CofO ALIZAH MAYAGOITIA
Smoke Detectors 7/13/2022 Approved ALIZAH MAYAGOITIA