5230 E HUB ST 90042

Certificate Information: 5230 E HUB ST 90042

Application / Permit
19014-20000-02224
Plan Check / Job No.
B19VN06996
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD'N of 488 SF NEW ADU TO (E) 400 SF GARGE , PER AB494 AND SB229 .
Permit Issued
Issued on 1/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 ABDUL CHEGENI
Green Plans Picked Up 6/6/2019 APPLICANT
Corrections Issued 6/7/2019 ABDUL CHEGENI
Quality Review Completed 6/14/2019 STEVEN KIM
Building Plans Picked Up 6/17/2019 APPLICANT
Plan Check Approved 11/27/2019 ABDUL CHEGENI
Issued 1/6/2020 LADBS
CofO in Progress 6/3/2021 HAMIK HARTOUNIAN
Permit Finaled 6/18/2021 DEROLD HAUFF
CofO Issued 6/18/2021 DEROLD HAUFF
Permit Finaled 6/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/30/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 8/30/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 8/30/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 8/30/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 8/30/2019 MARKOS PEREZ-BRAN
Highway dedication Cleared 8/30/2019 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 8/30/2019 GEORGE SUCHAND
Low Impact Development Cleared 8/30/2019 RYAN HUDSON
Permit Cleared 8/30/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 8/30/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/30/2019 MARKOS PEREZ-BRAN
Green Code Cleared 10/10/2019 DAVID MATSON
GPI Written Notices Cleared 10/22/2019 ABDUL CHEGENI
Grading Pre-Inspection Cleared 10/22/2019 ABDUL CHEGENI
Construction near power lines Cleared 10/26/2019 RIDWAN HARDY

Contact Information

Architect Sturgill,, Ben Curtis; Lic. No.: C23174 314 E BROADWAY # E      GLENDALE, CA 91205
Contractor Mozannar Construction Inc; Lic. No.: 695817-B 10721 BLOOMFIELD ST #1      NORTH HOLLYWOOD, CA 91602
Engineer Lombera,, Raymundo A; Lic. No.: L7740 135 S JACKSON STREET #202      GLENDALE, CA 91205
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 708 SOUTH REDONDO AVE      MANHATTAN BEACH, CA 90266
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/6/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/18/2020 Not Ready for Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 4/9/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/13/2020 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/13/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 4/29/2020 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 5/5/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/18/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/18/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 5/18/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 5/18/2020 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 5/18/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/21/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/2/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/2/2020 Approved HAMIK HARTOUNIAN
Gas Test 6/2/2020 Approved HAMIK HARTOUNIAN
Insulation 6/2/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/2/2020 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 6/2/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/5/2020 Approved CHRISTOPHER DELLEFIELD
Sewer 6/9/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 10/8/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 10/8/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 10/8/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 10/8/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 10/8/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/8/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 10/8/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 1/7/2021 Approved HAMIK HARTOUNIAN
Final 1/7/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 1/7/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 1/7/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Final 1/7/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/7/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/7/2021 Approved HAMIK HARTOUNIAN
Final 2/24/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/24/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Final 6/3/2021 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Approved HAMIK HARTOUNIAN