422 N BELLAGIO TER 90049
Certificate Information: 422 N BELLAGIO TER 90049
- Application / Permit
- 19014-20000-02194
- Plan Check / Job No.
- B19VN06929
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 79'-3" x 48'-10" IRREGULAR SHAPED 2-ND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
- Permit Issued
- Issued on 6/20/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | SARKIS HARABEDIAN |
| Green Plans Picked Up | 5/9/2019 | APPLICANT |
| Corrections Issued | 5/15/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 5/21/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 5/22/2019 | APPLICANT |
| Applicant returned to address corrections | 6/17/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/19/2019 | SARKIS HARABEDIAN |
| Issued | 6/20/2019 | LADBS |
| CofO in Progress | 11/16/2022 | CARLOS MATAMOROS |
| CofO in Progress | 11/16/2022 | CARLOS MATAMOROS |
| CofO in Progress | 11/16/2022 | CARLOS MATAMOROS |
| Permit Finaled | 11/30/2022 | DANIEL ORRANTE |
| CofO Issued | 11/30/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/30/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/30/2019 | ISRAEL TAMIRU |
| BHO/Hillside ordinance | Cleared | 5/30/2019 | ISRAEL TAMIRU |
| BHO/Hillside ordinance | Cleared | 5/30/2019 | ISRAEL TAMIRU |
| Hydrant and Access approval | Cleared | 5/30/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 5/30/2019 | ISRAEL TAMIRU |
| Green Code | Cleared | 6/11/2019 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2019 | JULIUS GARCIA |
| Low Impact Development | Cleared | 6/13/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/13/2019 | JULIUS GARCIA |
| GPI Written Notices | Cleared | 6/17/2019 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 6/17/2019 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Superior Home Builders Inc; Lic. No.: 875933-B | 6569 CLEOMOORE AVE WEST HILLS, CA 91307 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Pongracz-Bartha,, Ed; Lic. No.: GEO7673 | 10501 COLLETT AVE GRANADA HILLS, CA 91344 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2020 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 7/20/2020 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Inspection | 7/27/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Special/Order Compliance | 12/9/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/30/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 3/31/2021 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Approved | CARLOS MATAMOROS |
| Wood Frame | 5/6/2021 | Approved | CARLOS MATAMOROS |
| Deputy Steel/Welding | 5/24/2021 | Conditional Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/4/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 6/4/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2021 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 6/18/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 6/18/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/7/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 7/7/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 7/7/2021 | No Access for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 8/18/2021 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 10/1/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 10/4/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 10/28/2021 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 10/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 10/28/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/9/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/9/2021 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/9/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/15/2021 | Partial Approval | STEPHANIE SWANSON |
| Gas Test | 11/15/2021 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/15/2021 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/12/2022 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Rough | 1/12/2022 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/14/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 1/14/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/14/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 1/14/2022 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 1/14/2022 | Corrections Issued | CARLOS MATAMOROS |
| Drywall Nailing | 2/28/2022 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 2/28/2022 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 6/27/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 8/25/2022 | Approved | CARLOS MATAMOROS |
| Final | 8/25/2022 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 8/25/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 8/25/2022 | Approved | CARLOS MATAMOROS |
| Final | 11/15/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/15/2022 | Approved | CARLOS MATAMOROS |
| Green Building Final | 11/15/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 11/15/2022 | Approved | CARLOS MATAMOROS |