6743 N IRVINE AVE 91606
Certificate Information: 6743 N IRVINE AVE 91606
- Application / Permit
- 19014-20000-02184
- Plan Check / Job No.
- B19VN06898
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 30'-0" x 26'-5" IRREGULAR SHAPED ADDITION AND INTERIOR REMODEL TO THE (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 4/30/2019
- Issuing Office
- Valley
- Current Status
- Issued on 4/30/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
Submitted | 4/26/2019 | APPLICANT |
Assigned to Plan Check Engineer | 4/30/2019 | NIKTA MOUSAVI |
Plan Check Approved | 4/30/2019 | NIKTA MOUSAVI |
Issued | 4/30/2019 | LADBS |
Permit Application Clearance Information
Eng Process Fee Ord 176,300 | Cleared | 4/30/2019 | JOHN LIN |
Low Impact Development | Cleared | 4/30/2019 | ANDRES COVARRUBIAS |
Roof/Waste drainage to street | Cleared | 4/30/2019 | JOHN LIN |
Sewer availability | Cleared | 4/30/2019 | JOHN LIN |
Contact Information
Contractor | Owner-Builder | , |
Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
JOSE AVILA, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Footing/Foundation/Slab | 7/23/2019 | Corrections Issued | MISAEL ESPARZA |
Footing/Foundation/Slab | 8/2/2019 | Not Ready for Inspection | RAYMOND KEHOE |
Footing/Foundation/Slab | 8/23/2019 | Not Ready for Inspection | MISAEL ESPARZA |
Footing/Foundation/Slab | 9/5/2019 | Approved | MISAEL ESPARZA |
Floor/Roof Diaphrgm/Shear Wall | 1/30/2020 | Partial Approval | RAYMOND KEHOE |
Underground Mechanical | 1/30/2020 | Approved | RAYMOND KEHOE |
ELECTRICAL-Rough | 8/26/2020 | No Access for Inspection | DANIEL DREW |
HVAC-Rough | 8/26/2020 | No Access for Inspection | DANIEL DREW |
PLUMBING-Rough | 8/26/2020 | No Access for Inspection | DANIEL DREW |
ELECTRICAL-Rough | 8/28/2020 | Partial Approval | DANIEL DREW |
HVAC-Rough | 8/28/2020 | Not Ready for Inspection | DANIEL DREW |
PLUMBING-Rough | 8/28/2020 | Corrections Issued | DANIEL DREW |
BUILDING-Rough-Frame | 9/4/2020 | Corrections Issued | DANIEL DREW |
Green Building Rough | 9/4/2020 | Corrections Issued | DANIEL DREW |
PLUMBING-Rough | 9/4/2020 | Corrections Issued | DANIEL DREW |
PLUMBING-Rough | 9/10/2020 | Approved | DANIEL DREW |
Special/Order Compliance | 10/30/2023 | Partial Inspection | ROBERT GOLD |