4538 W AMBROSE AVE 90027
Certificate Information: 4538 W AMBROSE AVE 90027
- Application / Permit
- 19014-20000-02164
- Plan Check / Job No.
- B19VN06835
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-9.5" X 18'-3.5" DETACHED GARAGE AND (13'-3.5" X 19'-3.5") 2ND STORY ADDITION TO CREATE (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/9/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | RAPHAEL ROSAS |
| Corrections Issued | 5/13/2019 | RAPHAEL ROSAS |
| Quality Review Completed | 5/13/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 5/13/2019 | APPLICANT |
| Green Plans Picked Up | 5/13/2019 | APPLICANT |
| Applicant returned to address corrections | 8/19/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 9/3/2019 | RAPHAEL ROSAS |
| Issued | 9/9/2019 | LADBS |
| CofO in Progress | 2/20/2021 | JOSEPH MCGARRY |
| Permit Finaled | 2/23/2021 | DEROLD HAUFF |
| CofO Issued | 2/23/2021 | DEROLD HAUFF |
| Permit Finaled | 2/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/31/2019 | RIDWAN HARDY |
| Address approval | Cleared | 8/2/2019 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2019 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/2/2019 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/2/2019 | GABRIEL ROBLES |
| Green Code | Cleared | 8/8/2019 | DAVID MATSON |
| Grading Pre-Inspection | Cleared | 8/19/2019 | RAPHAEL ROSAS |
| ZI | Cleared | 8/27/2019 | LINDA LOU |
| GPI Written Notices | Cleared | 9/3/2019 | RAPHAEL ROSAS |
Contact Information
| Contractor | A A A Remodeling & Restoration Inc; Lic. No.: 859135-B | 7105 GERALD AVENUE VAN NUYS, CA 91406 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/7/2019 | Approved | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 10/9/2019 | Corrections Issued | BRAD BESCOS |
| PLUMBING-Rough | 10/9/2019 | Corrections Issued | BRAD BESCOS |
| Footing/Foundation/Slab | 1/23/2020 | Not Ready for Inspection | BRAD BESCOS |
| PLUMBING-Rough | 1/23/2020 | Not Ready for Inspection | BRAD BESCOS |
| Footing/Foundation/Slab | 1/30/2020 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 1/30/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 2/12/2020 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 2/12/2020 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 4/23/2020 | Partial Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2020 | Corrections Issued | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 5/8/2020 | Partial Inspection | JOSEPH MCGARRY |
| Shower Pan | 5/8/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Wood Construction | 5/13/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/14/2020 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 5/14/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 5/19/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 5/19/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/10/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/10/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/10/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/10/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/10/2020 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 6/10/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/15/2020 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 6/15/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/15/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 6/15/2020 | Conditional Approval | JOSEPH MCGARRY |
| Drywall Nailing | 6/24/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 6/24/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/24/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/21/2020 | Approved | JOSEPH MCGARRY |
| Final | 9/21/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 9/21/2020 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 9/21/2020 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 9/21/2020 | Approved | JOSEPH MCGARRY |
| Final | 11/4/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 2/5/2021 | OK to Issue CofO | JOSEPH MCGARRY |