13011 W ROSE AVE 90066

Certificate Information: 13011 W ROSE AVE 90066

Application / Permit
19014-20000-02152
Plan Check / Job No.
B19VN06802
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 19' 5" X 16' ACCESSORY DWELLING UNIT TO DETACHED 2-CAR GARAGE AND ADD 23' 6" X 34' 2ND STORY TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 8/22/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2019 APPLICANT
Green Plans Picked Up 5/24/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 GURUNATH NESARAJAH
Corrections Issued 6/5/2019 GURUNATH NESARAJAH
Quality Review Completed 6/7/2019 OMID HEDAYAT
Building Plans Picked Up 6/13/2019 APPLICANT
Plan Check Approved 8/22/2019 GURUNATH NESARAJAH
Issued 8/22/2019 LADBS
CofO in Progress 6/7/2022 PATRICK QUALEY
Permit Finaled 6/28/2022 DANIEL ORRANTE
Permit Finaled 6/28/2022 DANIEL ORRANTE
CofO Issued 6/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/2/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/2/2019 LEE GUILBEAUX
Sewer availability Cleared 8/2/2019 LEE GUILBEAUX
Specific Plan Cleared 8/2/2019 RINA LARA
ZI Cleared 8/2/2019 RINA LARA
ZI Cleared 8/2/2019 RINA LARA
GPI Written Notices Cleared 8/5/2019 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 8/5/2019 GURUNATH NESARAJAH
Green Code Cleared 8/7/2019 DAVID MATSON
Low Impact Development Cleared 8/13/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/13/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Djoneva,, Diana Ivanova; Lic. No.: C73805 3241 HENRIETTA AVE      LA CRESCENTA, CA 91214

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/28/2019 Corrections Issued JOHNNY MIRANDA
Pre-Inspection 10/28/2019 Partial Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 10/30/2019 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 10/30/2019 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/7/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/15/2020 Corrections Issued CRAIG DAVIS
Drywall Nailing 1/22/2020 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Partial Inspection JOHNNY MIRANDA
Green Building Rough 1/22/2020 Not Ready for Inspection JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 8/5/2020 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 8/26/2020 Corrections Issued ANTHONY MCDOWALL
HVAC-Rough 8/26/2020 Corrections Issued ANTHONY MCDOWALL
HVAC-Rough 8/26/2020 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Rough 9/4/2020 Approved JOHNNY MIRANDA
HVAC-Rough 9/4/2020 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 9/4/2020 Approved JOHNNY MIRANDA
Drywall Nailing 9/21/2020 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Corrections Issued JOHNNY MIRANDA
Green Building Rough 9/21/2020 Corrections Issued JOHNNY MIRANDA
Special/Order Compliance 9/21/2020 Partial Inspection PIERRE VEGA
BUILDING-Rough-Frame 10/30/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 10/30/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 10/30/2020 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 10/30/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 11/2/2020 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 12/4/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 12/4/2020 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 12/16/2020 Partial Approval JOHNNY MIRANDA
Shower Pan 12/16/2020 Approved JOHNNY MIRANDA
Insulation 12/22/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/24/2020 Corrections Issued ENRIQUE MIRELES
Green Building Rough 12/24/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/29/2021 Approved ENRIQUE MIRELES
Drywall Nailing 2/23/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 5/10/2021 Approved WILLIAM MICHALAK
PLUMBING-Rough 5/13/2021 Partial Inspection JUAN VALENZUELA
Gas Test 7/9/2021 Not Ready for Inspection JOHNNY MIRANDA
Gas Test 7/16/2021 Corrections Issued ENRIQUE MIRELES
Gas Test 8/6/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/7/2022 Corrections Issued PATRICK QUALEY
Final 4/7/2022 Corrections Issued PATRICK QUALEY
Footing/Foundation/Slab 4/7/2022 Approved PATRICK QUALEY
Green Building Final 4/7/2022 Corrections Issued PATRICK QUALEY
HVAC-Final 4/7/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 4/7/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Not Ready PATRICK QUALEY
Smoke Detectors 4/7/2022 Corrections Issued PATRICK QUALEY
Final 4/13/2022 Corrections Issued PATRICK QUALEY
Green Building Final 4/13/2022 Not Ready for Inspection PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/13/2022 SGSOV Not Ready PATRICK QUALEY
Smoke Detectors 4/13/2022 Not Ready for Inspection PATRICK QUALEY
ELECTRICAL-Final 4/19/2022 Corrections Issued PATRICK QUALEY
Final 4/19/2022 Corrections Issued PATRICK QUALEY
Green Building Final 4/19/2022 Approved PATRICK QUALEY
PLUMBING-Final 4/19/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Approved PATRICK QUALEY
Smoke Detectors 4/19/2022 Approved PATRICK QUALEY
Gas Test 4/22/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 5/31/2022 Approved PATRICK QUALEY
Final 5/31/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 5/31/2022 Approved PATRICK QUALEY
Final 6/7/2022 OK to Issue CofO PATRICK QUALEY
HVAC-Final 6/7/2022 Approved PATRICK QUALEY
Service/Power Release 6/23/2022 Approved RICHARD STEINBACH