6447 N LONGRIDGE AVE 91401

Certificate Information: 6447 N LONGRIDGE AVE 91401

Application / Permit
19014-20000-02144
Plan Check / Job No.
B19VN06777
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (29'-8"x 32'-0") 2ND STORY ABOVE (E) DETACHED REC. RM & CARPORT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 8/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 TROY DEGUZMAN
Corrections Issued 5/13/2019 TROY DEGUZMAN
Green Plans Picked Up 5/14/2019 APPLICANT
Quality Review Completed 5/17/2019 STEVEN KIM
Building Plans Picked Up 5/21/2019 APPLICANT
Applicant returned to address corrections 4/13/2021 TROY DEGUZMAN
Plan Check Approved 4/15/2021 TROY DEGUZMAN
Issued 4/15/2021 APPLICANT
CofO in Progress 7/27/2022 RAFAEL CORTES
Permit Finaled 8/16/2022 DANIEL ORRANTE
CofO Issued 8/16/2022 DANIEL ORRANTE
Permit Finaled 8/16/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 11/25/2019 RIDWAN HARDY
Green Code Cleared 1/9/2020 PARISA ZAHABI
Address approval Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/26/2021 JOHN CONNEALLY
Low Impact Development Cleared 2/26/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/1/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/3/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/22/2021 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/27/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Conditional Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/15/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 10/15/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/15/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/4/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/4/2021 Approved CHRISTOPHE COCHRAN
Green Building Rough 11/4/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/16/2021 Partial Approval ASHLEY THOMPSON
Shower Pan 11/16/2021 Not Ready for Inspection ASHLEY THOMPSON
Insulation 11/23/2021 Approved CHRISTOPHE COCHRAN
Shower Pan 11/23/2021 Approved CHRISTOPHE COCHRAN
Drywall Nailing 12/2/2021 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/2/2021 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 1/25/2022 Approved CHRISTOPHE COCHRAN
Final 3/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Final 3/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Not Ready CHRISTOPHE COCHRAN
Smoke Detectors 3/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 5/12/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 5/12/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/12/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 5/12/2022 Approved CHRISTOPHE COCHRAN
Final 7/21/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Final 7/21/2022 Approved RAFAEL CORTES
Final 7/26/2022 OK to Issue CofO RAFAEL CORTES