12005 W WASHINGTON PL 90066

Certificate Information: 12005 W WASHINGTON PL 90066

Application / Permit
19014-20000-02143
Plan Check / Job No.
B19VN06766
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (N) ACCESSORY DWELLING UNIT OVER CARPORT (30'-1" X 15'-7") PER LAMC 12.22A33(c)(e) TO (E) 2-STORY RETAIL/SFD BLDG; RE-STRIPE PARKING
Permit Issued
Issued on 9/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 RUDOLF KINAR MELIKOFF
Corrections Issued 5/13/2019 RUDOLF KINAR MELIKOFF
Quality Review Completed 5/14/2019 STEVEN KIM
Building Plans Picked Up 5/17/2019 APPLICANT
Disabled Access Plans Picked Up 5/17/2019 APPLICANT
Green Plans Picked Up 11/21/2019 APPLICANT
Applicant returned to address corrections 4/27/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/26/2022 NILOOFAR MEHRAIN
Plan Check Approved 8/1/2022 NILOOFAR MEHRAIN
Issued 9/2/2022 APPLICANT
CofO in Progress 12/26/2023 FARHAD DADBIN
Permit Finaled 1/3/2024 DAVID TSAU
CofO Issued 1/3/2024 DAVID TSAU
Permit Finaled 1/3/2024 DAVID TSAU

Permit Application Clearance Information

Green Code Cleared 5/11/2020 DAVID MATSON
Address approval Cleared 12/11/2020 ANTHONY MAINEZ
Hydrant and Access approval Cleared 3/25/2021 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 1/31/2022 NIKTA MOUSAVI
ZA Case Cleared 2/11/2022 DANG NGUYEN
Housing rent stabilization Cleared 2/14/2022 MICHAEL SOTO
Permit Cleared 3/18/2022 NIKTA MOUSAVI
Specific Plan Cleared 3/23/2022 PEDRO AYALA
DAS Clearance Cleared 4/1/2022 NORLITO MEDRANO
Address approval Cleared 4/4/2022 DINAH GARIN
Roof/Waste drainage to street Cleared 4/7/2022 NIKTA MOUSAVI

Contact Information

Contractor Owner-Builder       ,
Engineer Mauricio,, Omar; Lic. No.: C87487 947 E MERCED AVE      WEST COVINA, CA 91790

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/29/2022 Not Ready for Inspection NICK LAROCCA
Footing/Foundation/Slab 9/29/2022 Not Ready for Inspection NICK LAROCCA
Excavation/Setback/Form/Re-Bar 10/4/2022 Not Ready for Inspection GRANT WOODS
Footing/Foundation/Slab 10/5/2022 Partial Approval ALAN NOVAK
Deputy Reinf. Concrete 10/13/2022 Conditional Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 10/25/2022 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 10/27/2022 Approved GRANT WOODS
Deputy Reinf. Concrete 11/1/2022 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 12/19/2022 Corrections Issued GRANT WOODS
Deputy Drilled-In Anchors 1/4/2023 Conditional Approval AMANUEL BERHE
Excavation/Setback/Form/Re-Bar 1/5/2023 Partial Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Not Ready for Inspection SORIN CIRSTOIU
Green Building Rough 2/3/2023 Not Ready for Inspection SORIN CIRSTOIU
Wood Frame 2/3/2023 Not Ready for Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Not Ready for Inspection FARHAD DADBIN
Green Building Rough 2/22/2023 Approved MICHAEL PETRUSKO
Wood Frame 2/22/2023 Approved MICHAEL PETRUSKO
Deputy Wood Construction 5/11/2023 Approved FARHAD DADBIN
Floor/Roof Diaphrgm/Shear Wall 5/11/2023 Partial Approval FARHAD DADBIN
Special/Order Compliance 5/11/2023 Partial Approval FARHAD DADBIN
Insulation 5/17/2023 Corrections Issued FARHAD DADBIN
Drywall Nailing 5/22/2023 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 5/31/2023 Approved FARHAD DADBIN
Drywall Nailing 8/23/2023 Not Ready for Inspection FARHAD DADBIN
Drywall Nailing 10/18/2023 Approved FARHAD DADBIN
Final 10/18/2023 Not Ready for Inspection FARHAD DADBIN
Green Building Final 10/18/2023 Approved FARHAD DADBIN
Light Gage Steel Frame 10/18/2023 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/18/2023 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 10/18/2023 Not Ready for Inspection FARHAD DADBIN
Structural Steel Frame 10/18/2023 Not Ready for Inspection FARHAD DADBIN
Final 11/6/2023 Partial Approval FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 11/6/2023 SGSOV Approved FARHAD DADBIN
Smoke Detectors 11/6/2023 Approved FARHAD DADBIN
Structural Steel Frame 11/6/2023 Approved FARHAD DADBIN
Final 11/14/2023 Partial Approval FARHAD DADBIN
Final 12/13/2023 Conditional Approval FARHAD DADBIN
Final 12/26/2023 OK to Issue CofO FARHAD DADBIN