151 S THURSTON AVE 90049

Certificate Information: 151 S THURSTON AVE 90049

Application / Permit
19014-20000-02113
Plan Check / Job No.
B19VN06656
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 5'-1" X 14'-4" AND 10'-6" X 26'-11" TO AN (E) 2-STORY SFD PER ENGINEERING
Permit Issued
Issued on 7/18/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 JENNIFER LEE
Corrections Issued 5/14/2019 JENNIFER LEE
Quality Review Completed 5/15/2019 STEVEN KIM
Building Plans Picked Up 6/10/2019 APPLICANT
Green Plans Picked Up 6/10/2019 APPLICANT
Applicant returned to address corrections 7/9/2019 JENNIFER LEE
Plan Check Approved 7/17/2019 JENNIFER LEE
Issued 7/18/2019 LADBS
CofO in Progress 8/20/2020 CARLOS MATAMOROS
Permit Finaled 10/16/2021 DANIEL ORRANTE
CofO Issued 10/16/2021 DANIEL ORRANTE
Permit Finaled 10/16/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/9/2019 JENNIFER LEE
Eng Process Fee Ord 176,300 Cleared 7/17/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 7/17/2019 GUILLERMO PETRA
Sewer availability Cleared 7/17/2019 GUILLERMO PETRA
Green Code Cleared 7/18/2019 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/13/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 12/16/2019 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 12/21/2019 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 12/21/2019 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 12/23/2019 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 1/30/2020 Approved CARLOS MATAMOROS
Green Building Rough 1/30/2020 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Rough 1/30/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 2/19/2020 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 2/19/2020 Approved CARLOS MATAMOROS
Green Building Rough 2/19/2020 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 2/19/2020 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Rough 2/19/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 2/19/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 2/24/2020 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 2/26/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 2/26/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Approved CARLOS MATAMOROS
HVAC-Rough 3/4/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 3/9/2020 Approved CARLOS MATAMOROS
Green Building Rough 3/9/2020 Approved CARLOS MATAMOROS
MERV13>=Rough 3/9/2020 Approved CARLOS MATAMOROS
Insulation 3/11/2020 Approved CARLOS MATAMOROS
Drywall Nailing 3/12/2020 Partial Approval CARLOS MATAMOROS
Drywall Nailing 3/17/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 3/24/2020 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 3/25/2020 Approved TIM CHRISTENSEN
Final 6/29/2020 Corrections Issued CARLOS MATAMOROS
Footing/Foundation/Slab 6/29/2020 Approved CARLOS MATAMOROS
Green Building Final 6/29/2020 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Final 6/29/2020 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/29/2020 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 6/29/2020 Approved CARLOS MATAMOROS
Final 7/2/2020 Partial Approval CARLOS MATAMOROS
Gas Test 7/2/2020 Approved CARLOS MATAMOROS
Green Building Final 7/2/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Final 7/10/2020 Approved CARLOS MATAMOROS
Final 7/10/2020 Partial Approval CARLOS MATAMOROS
HVAC-Final 7/10/2020 Approved CARLOS MATAMOROS
PLUMBING-Final 7/10/2020 Approved CARLOS MATAMOROS
Final 8/20/2020 Partial Approval CARLOS MATAMOROS