5249-5251 N ALLOTT AVE 91401

Certificate Information: 5249-5251 N ALLOTT AVE 91401

Application / Permit
19014-20000-02098
Plan Check / Job No.
B19VN06595
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19'-11" X 22'-6" ATTACHED GARAGE AND ADD 2'-0" X 10'-6" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229, CONVERT (E) 9'-5" X 16'-2" BREEZEWAY FOR (N) BEDROOM, REMOVE (E) 1-STORY SFD W/ 27'-2" AND 31'-3" WALLS TO REMAIN AND ADD IRREGULAR 44'-2" X 78'-6" FOR (N) 1-STORY SFD PER ENGINEERING. NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 7/23/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2019 APPLICANT
Green Plans Picked Up 4/30/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 JENNIFER LEE
Corrections Issued 5/15/2019 JENNIFER LEE
Quality Review Completed 5/15/2019 STEVEN KIM
Building Plans Picked Up 5/17/2019 APPLICANT
Applicant returned to address corrections 6/3/2019 JENNIFER LEE
Plan Check Approved 6/6/2019 JENNIFER LEE
Issued 7/23/2019 LADBS
CofO in Progress 6/5/2020 CHARLES POWELL
CofO Issued 6/10/2020 DANIEL ORRANTE
Permit Finaled 6/10/2020 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 5/14/2019 PARISA ZAHABI
Address approval Cleared 5/21/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 5/21/2019 JOHN LIN
Sewer availability Cleared 5/21/2019 JOHN LIN
Low Impact Development Cleared 5/29/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 6/3/2019 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Morales,, Cesar Del Valle; Lic. No.: C76612 370 S COMMONWEALTH AVENUE #105      LOS ANGELES, CA 90020

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2019 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 8/13/2019 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 8/15/2019 Partial Approval THOMAS FINNILA
Underground Mechanical 9/10/2019 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/17/2019 Partial Approval THOMAS FINNILA
Underground Mechanical 9/17/2019 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/19/2019 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/20/2019 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/1/2019 Partial Approval JEFFREY PARD
Deputy Wood Construction 12/16/2019 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 12/17/2019 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/24/2019 Approved JEFFREY PARD
HVAC-Rough 12/24/2019 Approved JEFFREY PARD
Interior/Exterior Lathing 12/24/2019 Approved JEFFREY PARD
PLUMBING-Rough 12/24/2019 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/27/2019 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/27/2019 Approved CHRISTOPHE COCHRAN
Green Building Rough 12/27/2019 Approved CHRISTOPHE COCHRAN
Insulation 1/6/2020 Approved CHRISTOPHE COCHRAN
Shower Pan 1/6/2020 Approved CHRISTOPHE COCHRAN
Drywall Nailing 1/15/2020 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/15/2020 Approved CHRISTOPHE COCHRAN
Final 4/13/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/13/2020 Approved MISAEL ESPARZA
Green Building Final 4/13/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/13/2020 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 4/13/2020 Approved MISAEL ESPARZA
Final 4/27/2020 Partial Approval TROY SANDERS
Final 5/15/2020 No Access for Inspection CHARLES POWELL
Final 5/22/2020 Partial Approval CHARLES POWELL