9024 N ODESSA AVE 91343

Certificate Information: 9024 N ODESSA AVE 91343

Application / Permit
19014-20000-02068
Plan Check / Job No.
B19VN06477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21'-2" X 17'-0" ADDITION TO (E) SINGLE FAMILY DWELLING FOR NEW MASTER BEDROOM AND BATHROOM. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 6/1/2023
Issuing Office
Valley
Current Status
Issued on 6/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/22/2019 APPLICANT
Green Plans Picked Up 5/23/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 ROSENDO MEDINA
Corrections Issued 6/11/2019 ROSENDO MEDINA
Quality Review Completed 6/14/2019 OMID HEDAYAT
Building Plans Picked Up 6/19/2019 APPLICANT
Applicant returned to address corrections 1/30/2020 ROSENDO MEDINA
Applicant returned to address corrections 5/12/2020 ROSENDO MEDINA
Plan Check Approved 5/13/2020 ROSENDO MEDINA
Issued 6/1/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/27/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 9/27/2019 JEANETTE VONG
Sewer availability Cleared 9/27/2019 JEANETTE VONG
Green Code Cleared 10/2/2019 PARISA ZAHABI
Hydrant and Access approval Cleared 10/2/2019 GEORGE SUCHAND
Low Impact Development Cleared 1/9/2020 MARTIN FRAGOSO

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2320 SANTA CRUZ CT      TORRANCE, CA 90501

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/6/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 11/8/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 11/14/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 12/6/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/15/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/22/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 1/22/2024 Approved RAUL OLAGI
Green Building Rough 1/22/2024 Approved RAUL OLAGI
HVAC-Rough 1/22/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 1/22/2024 Approved RAUL OLAGI
PLUMBING-Rough 1/22/2024 Approved RAUL OLAGI
Insulation 1/24/2024 Approved RAUL OLAGI
Drywall Nailing 1/26/2024 Approved RAUL OLAGI
Excavation/Setback/Form/Re-Bar 2/15/2024 Approved RAUL OLAGI
Final 4/12/2024 Corrections Issued RAUL OLAGI
Green Building Final 4/12/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/12/2024 Approved RAUL OLAGI
Special/Order Compliance 4/12/2024 Not Ready for Inspection SALVADOR MARTINEZ