8460-8462 N SHARP AVE 91352

Certificate Information: 8460-8462 N SHARP AVE 91352

Application / Permit
19014-20000-01974
Plan Check / Job No.
B19VN06193
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
38'-2" X 25' GROUND FLOOR ADDITION TO EX. SFD FOR NEW BEDROOM/ BATHROOM AND FAMILY ROOM. 25' X 19' 2ND STORY ADDITION FOR NEW BEDROOM/BATHROOM. 38' X 21' IRREGULAR ADDITION TO EX. DETACHED GARAGE AND CONVERT INTO ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (e). WORK PER ENGINEER. "COMPLY WITH DEPARTMENT ORDER effective date 06/19/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/28/2022
Issuing Office
Valley
Current Status
Issued on 7/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/17/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 ROSENDO MEDINA
Corrections Issued 5/28/2019 ROSENDO MEDINA
Quality Review Completed 5/31/2019 OMID HEDAYAT
Green Plans Picked Up 5/31/2019 APPLICANT
Applicant returned to address corrections 5/5/2022 ROSENDO MEDINA
Applicant returned to address corrections 6/14/2022 ROSENDO MEDINA
Applicant returned to address corrections 6/28/2022 ROSENDO MEDINA
Building Plans Picked Up 6/29/2022 APPLICANT
Plan Check Approved 7/28/2022 ROSENDO MEDINA
Issued 7/28/2022 APPLICANT

Permit Application Clearance Information

Certificate of Compliance Cleared 3/25/2022 MARC WOERSCHING
Low Impact Development Cleared 3/31/2022 ANDRES COVARRUBIAS
Address approval Cleared 5/20/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/24/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/24/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/2/2022 DAGOVERTO GUERRERO
Green Code Cleared 6/28/2022 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/15/2022 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 8/15/2022 Corrections Issued MICKEY YAMASHITA
Deputy Drilled-In Anchors 9/27/2022 No Result Entered MARSHALL RUMPF
ELECTRICAL-Rough 10/3/2022 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 10/3/2022 Corrections Issued MICKEY YAMASHITA
PLUMBING-Rough 10/3/2022 Corrections Issued MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 11/29/2022 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 11/29/2022 Corrections Issued MICKEY YAMASHITA
Sewer 11/29/2022 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 2/7/2023 Corrections Issued MICKEY YAMASHITA
Sewer 2/7/2023 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 2/14/2023 Partial Approval MICKEY YAMASHITA
PLUMBING-Rough 2/14/2023 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 4/21/2023 Not Ready for Inspection LEO MILBAUER
Footing/Foundation/Slab 4/21/2023 Conditional Approval LEO MILBAUER
PLUMBING-Rough 4/21/2023 Not Ready for Inspection LEO MILBAUER
ELECTRICAL-Rough 5/5/2023 Partial Inspection LEO MILBAUER
Footing/Foundation/Slab 5/5/2023 Partial Inspection LEO MILBAUER
PLUMBING-Rough 5/5/2023 Partial Inspection LEO MILBAUER
Wood Frame 5/5/2023 Partial Inspection LEO MILBAUER
ELECTRICAL-Rough 6/9/2023 Not Ready for Inspection LEO MILBAUER
Wood Frame 6/9/2023 Not Ready for Inspection LEO MILBAUER
BUILDING-Rough-Frame 8/16/2023 Partial Inspection LEO MILBAUER
ELECTRICAL-Rough 8/16/2023 Corrections Issued LEO MILBAUER
Footing/Foundation/Slab 8/16/2023 Partial Inspection LEO MILBAUER
Green Building Rough 8/16/2023 Partial Inspection LEO MILBAUER
HVAC-Rough 8/16/2023 Partial Inspection LEO MILBAUER
PLUMBING-Rough 8/16/2023 Partial Inspection LEO MILBAUER
Rough-Elec/Plmb/HVAC 8/16/2023 Partial Inspection LEO MILBAUER
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Not Ready LEO MILBAUER
Wood Frame 8/16/2023 Partial Inspection LEO MILBAUER
Insulation 10/3/2023 Partial Inspection LEO MILBAUER
Rough-Elec/Plmb/HVAC 10/3/2023 Partial Inspection LEO MILBAUER
Wood Frame 10/3/2023 Partial Inspection LEO MILBAUER
Drywall Nailing 10/24/2023 Partial Inspection LEO MILBAUER
Green Building Rough 10/24/2023 Partial Inspection LEO MILBAUER
Interior/Exterior Lathing 10/24/2023 Partial Inspection LEO MILBAUER
PLUMBING-Rough 10/24/2023 Partial Inspection LEO MILBAUER
Wood Frame 10/24/2023 Partial Inspection LEO MILBAUER
Shower Pan 1/17/2024 Approved LEO MILBAUER
ELECTRICAL-Rough 4/19/2024 Partial Inspection LEO MILBAUER
PLUMBING-Rough 4/19/2024 Approved LEO MILBAUER
Rough-Elec/Plmb/HVAC 11/19/2024 Approved LEO MILBAUER
Service/Power Release 11/19/2024 Not Ready for Inspection LEO MILBAUER
Deputy Drilled-In Anchors 2/18/2025 Conditional Approval LEO MILBAUER
Excavation/Setback/Form/Re-Bar 2/20/2025 Approved LEO MILBAUER
Footing/Foundation/Slab 2/20/2025 Approved LEO MILBAUER
ELECTRICAL-Rough 5/5/2025 Approved LEO MILBAUER
PLUMBING-Rough 5/5/2025 Approved LEO MILBAUER
Wood Frame 5/5/2025 Approved LEO MILBAUER
Deputy Wood Construction 5/28/2025 Conditional Approval LEO MILBAUER
BUILDING-Rough-Frame 5/30/2025 Approved LEO MILBAUER
Drywall Nailing 5/30/2025 Approved LEO MILBAUER
Footing/Foundation/Slab 5/30/2025 Approved LEO MILBAUER
Green Building Rough 5/30/2025 Approved LEO MILBAUER
Insulation 5/30/2025 Approved LEO MILBAUER
Interior/Exterior Lathing 7/11/2025 Approved MARK VAN SLOOTEN
Shower Pan 7/11/2025 Approved MARK VAN SLOOTEN
Final 10/2/2025 Corrections Issued MICKEY YAMASHITA
Green Building Final 10/2/2025 Corrections Issued MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 10/2/2025 SGSOV Approved MICKEY YAMASHITA
Smoke Detectors 10/2/2025 Corrections Issued MICKEY YAMASHITA
Final 10/24/2025 Conditional Approval MARK VAN SLOOTEN
Green Building Final 10/24/2025 Approved MARK VAN SLOOTEN
Smoke Detectors 10/24/2025 Approved MARK VAN SLOOTEN