19138 W VANOWEN ST 91335

Certificate Information: 19138 W VANOWEN ST 91335

Application / Permit
19014-20000-01953
Plan Check / Job No.
B19VN06087
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF EX DET GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. SEE COMMENTS.
Permit Issued
Issued on 3/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2019 APPLICANT
Assigned to Plan Check Engineer 4/16/2019 HAYATO TSUCHIYA
Corrections Issued 4/17/2019 HAYATO TSUCHIYA
Building Plans Picked Up 4/18/2019 APPLICANT
Plan Check Approved 6/10/2019 HAYATO TSUCHIYA
Issued 3/20/2020 LADBS
CofO in Progress 9/6/2025 ROBERT GOLD
Permit Finaled 9/11/2025 MICHAEL PELHAM
CofO Issued 9/11/2025 MICHAEL PELHAM
Permit Finaled 9/11/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 5/23/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 5/23/2019 JOHN LIN
Roof/Waste drainage to street Cleared 5/23/2019 JOHN LIN
Sewer availability Cleared 5/23/2019 JOHN LIN
ZI Cleared 5/23/2019 TOM HENRY

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadkhanlou,, Amirhosein; Lic. No.: C87550 1812 WESTHOLME AVE APT 11      LOS ANGELES, CA 90025

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2020 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/1/2020 Approved VINCENT HANLEY
PLUMBING-Rough 4/1/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/14/2020 Partial Approval VINCENT HANLEY
Green Building Rough 4/21/2020 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 4/21/2020 Approved VINCENT HANLEY
Sewer 4/21/2020 Corrections Issued VINCENT HANLEY
Insulation 4/24/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/24/2020 Approved VINCENT HANLEY
Drywall Nailing 4/28/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/5/2020 Approved VINCENT HANLEY
Underground Mechanical 5/5/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/18/2020 Approved VINCENT HANLEY
Final 6/18/2020 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/18/2020 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 6/18/2020 Approved VINCENT HANLEY
Final 8/16/2022 Corrections Issued JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Approved JEFFREY BULL
Final 9/22/2022 Not Ready for Inspection JEFFREY BULL
Service/Power Release 9/22/2022 Approved JEFFREY BULL
Final 9/6/2025 OK to Issue CofO ROBERT GOLD