2742 S GLENDON AVE 90064

Certificate Information: 2742 S GLENDON AVE 90064

Application / Permit
19014-20000-01836
Plan Check / Job No.
B19VN05722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove 4'-1" x 19'-5" portion of the detached garage. Add 6' x 13'-2" and 4'-1" x 19'-5" and convert 13'-2" x 19'-5" portion of the garage into an Accessory Dwelling Unit per AB 494 and SB 229. All work per wfpp.
Permit Issued
Issued on 2/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2019 APPLICANT
Assigned to Plan Check Engineer 4/10/2019 MARVEL DELACRUZ
Corrections Issued 4/10/2019 MARVEL DELACRUZ
Applicant returned to address corrections 1/30/2020 HAYATO TSUCHIYA
Plan Check Approved 1/30/2020 HAYATO TSUCHIYA
No Progress 1/30/2020 HAYATO TSUCHIYA
Plan Check Approved 1/31/2020 ANGELICA MARTINEZ
Issued 2/19/2020 LADBS
CofO in Progress 5/28/2021 OGANES TARAKHCHYAN
Permit Finaled 6/1/2021 KENNETH NAGLE
CofO Issued 6/1/2021 KENNETH NAGLE
Permit Finaled 6/1/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 4/10/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 4/10/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 4/10/2019 GUILLERMO PETRA
Construction near power lines Cleared 8/1/2019 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/9/2019 MARVEL DELACRUZ
Sewer availability Cleared 12/9/2019 APEKSHYA BAJRACHARYA
Flood clearance Cleared 1/29/2020 RAYMOND LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2020 No Access for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/27/2021 Approved OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 5/27/2021 Approved OGANES TARAKHCHYAN
FLOOD-Proofing Certificate 5/27/2021 Approved OGANES TARAKHCHYAN
Final 5/27/2021 OK to Issue CofO OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/27/2021 Approved OGANES TARAKHCHYAN
Green Building Final 5/27/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 5/27/2021 Approved OGANES TARAKHCHYAN
MERV13>=Final 5/27/2021 Approved OGANES TARAKHCHYAN
MERV13>=Rough 5/27/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 5/27/2021 Approved OGANES TARAKHCHYAN