11167 W HORTENSE ST 91602

Certificate Information: 11167 W HORTENSE ST 91602

Application / Permit
19014-20000-01814
Plan Check / Job No.
B19VN05652
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO-STORY GROUND ADDITION & CONVERT (E) DETACHED GARAGE TO AN IRREGULAR 18'6"x27' ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 10/31/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 LUIS RINCON
Green Plans Picked Up 5/14/2019 APPLICANT
Corrections Issued 5/17/2019 LUIS RINCON
Quality Review Completed 5/21/2019 OMID HEDAYAT
Building Plans Picked Up 5/23/2019 APPLICANT
Applicant returned to address corrections 2/20/2020 LUIS RINCON
Plan Check Approved 3/6/2020 LUIS RINCON
Issued 10/31/2023 APPLICANT
CofO in Progress 4/17/2025 JAVIER RAMOS JR
CofO Issued 5/12/2025 RUBEN SALAS
Permit Finaled 5/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/23/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 7/23/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 7/23/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 8/6/2019 DAVID MATSON
Low Impact Development Cleared 1/23/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 3/3/2020 GABRIEL ROBLES

Contact Information

Architect , ; Lic. No.: C34210       SHERMAN OAKS, CA 91413
Contractor Unlimited Concepts & Development Inc; Lic. No.: 660025-B PO BOX 55401      SHERMAN OAKS, CA 91413

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 12/1/2023 Approved RYAN SALAZAR
PLUMBING-Rough 12/1/2023 Partial Approval RYAN SALAZAR
Pre-Inspection 12/1/2023 Partial Inspection RYAN SALAZAR
Sewer 12/1/2023 Not Ready for Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Corrections Issued KIRK SANDERS
Wood Frame 1/29/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 3/22/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval KIRK SANDERS
Underground Mechanical 3/22/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 4/2/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 4/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Gas Test 4/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 4/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 4/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 4/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 4/2/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/9/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 4/9/2024 Corrections Issued MICHEL ABAJAN
Green Building Rough 4/9/2024 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 4/9/2024 Corrections Issued MICHEL ABAJAN
MERV13>=Rough 4/9/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/9/2024 Partial Approval MICHEL ABAJAN
Insulation 4/12/2024 Corrections Issued CHRISTOPHER ROJAS
Pre-Inspection 4/18/2024 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 4/18/2024 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 5/10/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/10/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 5/10/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 5/10/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 5/10/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/10/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 5/17/2024 Approved CHRISTOPHER ROJAS
Shower Pan 5/29/2024 Approved LEONARD ROSS II
Interior/Exterior Lathing 5/31/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/4/2024 Partial Approval CHRISTOPHER ROJAS
Final 7/19/2024 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Approved CHRISTOPHER ROJAS
Final 8/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 8/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 8/5/2024 Approved CHRISTOPHER ROJAS
Smoke Detectors 8/5/2024 Approved CHRISTOPHER ROJAS
Final 3/4/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 3/4/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/11/2025 Approved JAVIER RAMOS JR
Final 4/11/2025 OK to Issue CofO JAVIER RAMOS JR