3125 S HADDINGTON DR 90064

Certificate Information: 3125 S HADDINGTON DR 90064

Application / Permit
19014-20000-01757
Plan Check / Job No.
B19VN05486
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO ENTIRE SFD EXCEPT 9.83LF OF SOUTH PORTION OF 1ST FLR & ALL (E) GARAGE WALLS BELOW AND EXTEND (E) BASEMENT & 1ST FLOOR AND ADD 2ND FLOOR TO (E) 1-STORY SFD W/ ATTACHED GARAGE & BASEMENT; MAJOR INTERIOR REMODEL (NFPA-13R FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 7/19/2019
Issuing Office
West Los Angeles
Current Status
CofO in Progress on 10/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/5/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 NILOOFAR MEHRAIN
Corrections Issued 4/22/2019 NILOOFAR MEHRAIN
Quality Review Completed 4/25/2019 CHON CHIO KUO
Building Plans Picked Up 4/25/2019 APPLICANT
Green Plans Picked Up 4/25/2019 APPLICANT
Applicant returned to address corrections 6/3/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/20/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/1/2019 NILOOFAR MEHRAIN
Plan Check Approved 7/18/2019 NILOOFAR MEHRAIN
Issued 7/19/2019 LADBS
CofO in Progress 12/31/2020 KEVIN SARGSYAN
No Progress 2/23/2023 DAVID FEILER
CofO in Progress 10/12/2024 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2019 CELINA MORENO
Sewer availability Cleared 5/6/2019 CELINA MORENO
Hydrant and Access approval Cleared 5/23/2019 GILBERT URREA
Low Impact Development Cleared 5/23/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 5/23/2019 ELAINE LEI
Excavation more than 5-ft deep Cleared 6/3/2019 CALOSHA APPROVED
GPI Written Notices Cleared 6/3/2019 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 6/3/2019 NILOOFAR MEHRAIN
Green Code Cleared 6/17/2019 DAVID MATSON
Haul Route Cleared 7/1/2019 NILOOFAR MEHRAIN

Contact Information

Contractor I D C S Corporation; Lic. No.: 995061-B 485 SOUTH ROBERTSON BLVD STE 8      BEVERLY HILLS, CA 90211
Engineer Minassian,, Andre Melik; Lic. No.: C33813 P O BOX 29216      LOS ANGELES, CA 90029
Engineer Nguyen,, Tuan Minh; Lic. No.: S5883 5552 W 123RD PLACE      HAWTHORNE, CA 90250

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/18/2019 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/15/2020 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 2/3/2020 Partial Approval EVAN COOPER
Deputy Wood Construction 2/19/2020 Conditional Approval RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Approved RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/18/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 4/30/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 5/22/2020 Corrections Issued CRAIG DAVIS
HVAC-Rough 5/22/2020 Corrections Issued CRAIG DAVIS
Wood Frame 5/22/2020 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 5/28/2020 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 6/5/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 6/5/2020 Approved KEVIN SARGSYAN
Green Building Rough 6/5/2020 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 6/5/2020 Approved KEVIN SARGSYAN
MERV13>=Rough 6/5/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 6/5/2020 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 6/10/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 6/10/2020 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 6/10/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/15/2020 Approved KEVIN SARGSYAN
Wood Frame 6/15/2020 Approved KEVIN SARGSYAN
Insulation 6/22/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 6/22/2020 Approved KEVIN SARGSYAN
Shower Pan 6/22/2020 Approved KEVIN SARGSYAN
Drywall Nailing 6/30/2020 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 6/30/2020 Approved KEVIN SARGSYAN
Sewer 6/30/2020 Corrections Issued KEVIN SARGSYAN
Drywall Nailing 7/6/2020 Approved KEVIN SARGSYAN
Sewer 7/6/2020 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 9/1/2020 Approved KEVIN SARGSYAN
Underground Mechanical 11/5/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 11/20/2020 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 11/20/2020 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 11/20/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Final 11/20/2020 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 11/20/2020 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 12/9/2020 Approved KEVIN SARGSYAN
Final 12/9/2020 Corrections Issued KEVIN SARGSYAN
Gas Test 12/9/2020 Approved KEVIN SARGSYAN
Green Building Final 12/9/2020 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 12/9/2020 Approved KEVIN SARGSYAN
MERV13>=Final 12/9/2020 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/9/2020 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 12/9/2020 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 12/9/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/14/2020 Approved KEVIN SARGSYAN
HVAC-Final 12/14/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 12/14/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 12/16/2020 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 12/16/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 12/16/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 12/18/2020 Approved KEVIN SARGSYAN
HVAC-Final 12/18/2020 Approved KEVIN SARGSYAN
PLUMBING-Final 12/18/2020 Approved KEVIN SARGSYAN
Final 12/21/2020 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 12/21/2020 Not Ready for Inspection KEVIN SARGSYAN
Final 12/29/2020 Not Ready for Inspection KEVIN SARGSYAN
Service/Power Release 12/29/2020 Approved KEVIN SARGSYAN
Service/Power Release 12/30/2020 Partial Inspection KEVIN SARGSYAN
Final 12/31/2020 Not Ready for Inspection KEVIN SARGSYAN
Special/Order Compliance 2/26/2021 Partial Inspection KENNETH NAGLE
Special/Order Compliance 3/2/2021 Corrections Issued KENNETH NAGLE
Final 10/12/2024 Corrections Issued MICHAEL PELHAM