6326-6328 N ETHEL AVE 91401

Certificate Information: 6326-6328 N ETHEL AVE 91401

Application / Permit
19014-20000-01752
Plan Check / Job No.
B19VN05465
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert 8' 9" x 20' irregular-shaped portion of (E) 2-car garage to recreation room, convert 3' 6" x 12' portion of recreation room to accessory dwelling unit stairs, add 10' x 19' to recreation room, add 30' 4" x 19' 2nd story accessory dwelling unit above 1-car garage & recreation room per AB 494 & SB 229 and add 4' x 16' patio cover to front of (e) single family dwelling. All work done per structural engineering.
Permit Issued
Issued on 7/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 GURUNATH NESARAJAH
Green Plans Picked Up 5/2/2019 APPLICANT
Corrections Issued 5/16/2019 GURUNATH NESARAJAH
Quality Review Completed 5/16/2019 OMID HEDAYAT
Building Plans Picked Up 5/22/2019 APPLICANT
Plan Check Approved 6/20/2019 GURUNATH NESARAJAH
Issued 7/10/2019 LADBS
CofO in Progress 12/8/2020 BRENDAN LOONEY
Permit Finaled 4/17/2021 MICHAEL SMITH
CofO Issued 4/17/2021 MICHAEL SMITH
Permit Finaled 4/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/23/2019 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 6/12/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 6/12/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 6/13/2019 MICHAEL AYERS
Low Impact Development Cleared 6/13/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/13/2019 MARKOS PEREZ-BRAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/2/2020 Not Ready for Inspection GREG ALLTON
PLUMBING-Rough 1/3/2020 Partial Approval GREG ALLTON
Pre-Inspection 2/21/2020 Partial Approval GREG ALLTON
Wood Frame 3/12/2020 Not Ready for Inspection GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Partial Approval GREG ALLTON
BUILDING-Rough-Frame 4/15/2020 Corrections Issued BRENDAN LOONEY
HVAC-Rough 4/15/2020 No Access for Inspection BRENDAN LOONEY
PLUMBING-Rough 4/15/2020 Approved BRENDAN LOONEY
Gas Test 4/24/2020 Partial Approval BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 4/24/2020 Approved BRENDAN LOONEY
Wood Frame 4/24/2020 Conditional Approval BRENDAN LOONEY
Interior/Exterior Lathing 5/1/2020 Partial Approval BRENDAN LOONEY
Shower Pan 5/1/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 9/8/2020 Approved DANIEL DREW
Drywall Nailing 9/8/2020 Approved DANIEL DREW
Final 9/8/2020 Corrections Issued DANIEL DREW
Footing/Foundation/Slab 9/8/2020 Approved DANIEL DREW
Green Building Final 9/8/2020 Corrections Issued DANIEL DREW
Green Building Rough 9/8/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Approved DANIEL DREW
Smoke Detectors 9/8/2020 Approved DANIEL DREW
Final 10/9/2020 No Access for Inspection BRENDAN LOONEY
Green Building Final 10/9/2020 No Access for Inspection BRENDAN LOONEY
Final 11/4/2020 Corrections Issued BRENDAN LOONEY
Green Building Final 11/4/2020 Not Ready for Inspection BRENDAN LOONEY
Final 12/7/2020 OK to Issue CofO BRENDAN LOONEY
Green Building Final 12/7/2020 Approved BRENDAN LOONEY