6326-6328 N ETHEL AVE 91401
Certificate Information: 6326-6328 N ETHEL AVE 91401
- Application / Permit
- 19014-20000-01752
- Plan Check / Job No.
- B19VN05465
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert 8' 9" x 20' irregular-shaped portion of (E) 2-car garage to recreation room, convert 3' 6" x 12' portion of recreation room to accessory dwelling unit stairs, add 10' x 19' to recreation room, add 30' 4" x 19' 2nd story accessory dwelling unit above 1-car garage & recreation room per AB 494 & SB 229 and add 4' x 16' patio cover to front of (e) single family dwelling. All work done per structural engineering.
- Permit Issued
- Issued on 7/10/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | GURUNATH NESARAJAH |
| Green Plans Picked Up | 5/2/2019 | APPLICANT |
| Corrections Issued | 5/16/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 5/16/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 5/22/2019 | APPLICANT |
| Plan Check Approved | 6/20/2019 | GURUNATH NESARAJAH |
| Issued | 7/10/2019 | LADBS |
| CofO in Progress | 12/8/2020 | BRENDAN LOONEY |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
| CofO Issued | 4/17/2021 | MICHAEL SMITH |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 6/12/2019 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 6/13/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 6/13/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/13/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/2/2020 | Not Ready for Inspection | GREG ALLTON |
| PLUMBING-Rough | 1/3/2020 | Partial Approval | GREG ALLTON |
| Pre-Inspection | 2/21/2020 | Partial Approval | GREG ALLTON |
| Wood Frame | 3/12/2020 | Not Ready for Inspection | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2020 | Partial Approval | GREG ALLTON |
| BUILDING-Rough-Frame | 4/15/2020 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 4/15/2020 | No Access for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 4/15/2020 | Approved | BRENDAN LOONEY |
| Gas Test | 4/24/2020 | Partial Approval | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 4/24/2020 | Approved | BRENDAN LOONEY |
| Wood Frame | 4/24/2020 | Conditional Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/1/2020 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 5/1/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 9/8/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 9/8/2020 | Approved | DANIEL DREW |
| Final | 9/8/2020 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 9/8/2020 | Approved | DANIEL DREW |
| Green Building Final | 9/8/2020 | Corrections Issued | DANIEL DREW |
| Green Building Rough | 9/8/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/8/2020 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 9/8/2020 | Approved | DANIEL DREW |
| Final | 10/9/2020 | No Access for Inspection | BRENDAN LOONEY |
| Green Building Final | 10/9/2020 | No Access for Inspection | BRENDAN LOONEY |
| Final | 11/4/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 11/4/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 12/7/2020 | OK to Issue CofO | BRENDAN LOONEY |
| Green Building Final | 12/7/2020 | Approved | BRENDAN LOONEY |