- ADD 21'-9" x 15'-4" AND 5'-6" x 20' TO AND CONVERT (E) 18' x 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2019 | JENNIFER LEE |
| Corrections Issued | 4/17/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 8/26/2019 | RARES BODEA |
| Plan Check Approved | 9/10/2019 | ANGELICA MARTINEZ |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 5/10/2024 | MATTHEW NELSON |
| Permit Finaled | 5/30/2024 | RUBEN SALAS |
| CofO Issued | 5/30/2024 | RUBEN SALAS |
| Permit Finaled | 5/30/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 7/26/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/26/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Gutierrez Brother Builders Inc; Lic. No.: 1057968-B | 14519 PADDOCK STREET SYLMAR, CA 91342 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/9/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 1/11/2024 | Approved | JENNIFER RABUCHIN |
| Gas Test | 1/11/2024 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Barrier | 1/11/2024 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 1/11/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/11/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/26/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/26/2024 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 1/26/2024 | Corrections Issued | MATTHEW NELSON |
| METHANE-Rough | 1/26/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/26/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 1/30/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/30/2024 | Approved | MATTHEW NELSON |
| Insulation | 2/1/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/1/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/6/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/6/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/6/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 5/8/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 5/8/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/8/2024 | Approved | MATTHEW NELSON |
| HVAC-Final | 5/8/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 5/8/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/8/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/8/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/8/2024 | Approved | MATTHEW NELSON |
| Final | 5/9/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 5/9/2024 | Approved | MATTHEW NELSON |