2714 W AVENUE 31 90065

Certificate Information: 2714 W AVENUE 31 90065

Application / Permit
19014-20000-01581
Plan Check / Job No.
B19VN04942
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13'-11" X 16'-7"ADDITION TO THE (E) ONE STORY SFD. WORK PER WFPP
Permit Issued
Issued on 8/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 2/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 NIKTA MOUSAVI
Corrections Issued 3/28/2019 NIKTA MOUSAVI
Applicant returned to address corrections 7/24/2019 ARTIN ZARUKIAN
Plan Check Approved 8/6/2019 HAYATO TSUCHIYA
Issued 8/20/2019 LADBS
CofO in Progress 2/11/2020 HAMIK HARTOUNIAN
Permit Finaled 2/15/2020 DEROLD HAUFF
CofO Issued 2/15/2020 DEROLD HAUFF
Permit Finaled 2/15/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/3/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/3/2019 LEE GUILBEAUX
Sewer availability Cleared 4/3/2019 LEE GUILBEAUX
Grading Pre-Inspection Cleared 7/24/2019 NIKTA MOUSAVI
Supp. Use District POD/CDO/TDO Cleared 8/5/2019 ADRINEH MELKONIAN
ZI Cleared 8/5/2019 ADRINEH MELKONIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/26/2019 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/3/2019 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/5/2019 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2019 Partial Approval HAMIK HARTOUNIAN
Insulation 10/3/2019 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/3/2019 Approved HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 10/3/2019 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 10/9/2019 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/9/2019 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/6/2019 No Access for Inspection HAMIK HARTOUNIAN
Final 12/6/2019 No Access for Inspection HAMIK HARTOUNIAN
Green Building Final 12/6/2019 No Access for Inspection HAMIK HARTOUNIAN
Green Building Rough 12/6/2019 No Access for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/6/2019 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 12/6/2019 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/12/2019 Approved HAMIK HARTOUNIAN
Final 12/12/2019 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Final 1/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 1/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 1/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/16/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/5/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 2/5/2020 Approved HAMIK HARTOUNIAN
Final 2/5/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 2/5/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 2/5/2020 Approved HAMIK HARTOUNIAN
HVAC-Final 2/5/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Final 2/5/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/5/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 2/5/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/6/2020 No Access for Inspection HAMIK HARTOUNIAN
Final 2/10/2020 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/10/2020 SGSOV Approved HAMIK HARTOUNIAN