936-938 N DEXTER ST 90042
Certificate Information: 936-938 N DEXTER ST 90042
- Application / Permit
- 19014-20000-01556
- Plan Check / Job No.
- B19VN04855
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX. 17'4" x 35'0" (IRR. SHAPE) CRAWL SPACE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/12/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | JEFFREY TANGONAN |
| Corrections Issued | 3/28/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 4/1/2019 | APPLICANT |
| Issued | 4/12/2019 | LADBS |
| CofO in Progress | 3/16/2020 | CHARLES BOGHOSKHAN |
| Permit Finaled | 3/21/2020 | DEROLD HAUFF |
| CofO Issued | 3/21/2020 | DEROLD HAUFF |
| Permit Finaled | 3/21/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/2/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/15/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 11/15/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/9/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/9/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/9/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 12/9/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 12/16/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 12/17/2019 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 12/23/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2019 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/8/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/8/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 1/8/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/8/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/8/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/8/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/10/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/10/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/17/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/17/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 1/17/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 1/17/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 1/17/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/17/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 1/22/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/22/2020 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 1/28/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 1/28/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 2/12/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/12/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 2/20/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 2/20/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Final | 2/20/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/20/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/20/2020 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 2/24/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
| Sewer | 2/24/2020 | No Access for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/27/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 2/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/27/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/27/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/27/2020 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 3/4/2020 | Conditional Approval | CHARLES BOGHOSKHAN |
| Smoke Detectors | 3/4/2020 | Approved | CHARLES BOGHOSKHAN |
| Final | 3/13/2020 | OK to Issue CofO | CHARLES BOGHOSKHAN |