4717-4719 N LOWELL AVE 91214
Certificate Information: 4717-4719 N LOWELL AVE 91214
- Application / Permit
- 19014-20000-01481
- Plan Check / Job No.
- B19VN04652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 25'-0" X 32'-9" ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 TO AN (E) 1-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/28/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2019 | APPLICANT |
| Green Plans Picked Up | 4/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | JENNIFER LEE |
| Corrections Issued | 4/9/2019 | JENNIFER LEE |
| Quality Review Completed | 4/9/2019 | STEVEN KIM |
| Building Plans Picked Up | 4/10/2019 | APPLICANT |
| Plan Check Approved | 6/26/2019 | JENNIFER LEE |
| Issued | 6/28/2019 | LADBS |
| CofO in Progress | 3/2/2022 | MATTHEW NELSON |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2019 | ELAINE LEI |
| Green Code | Cleared | 4/24/2019 | PARISA ZAHABI |
| Private street | Cleared | 4/25/2019 | ANNA VIDAL |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2019 | KAREN LE |
| Low Impact Development | Cleared | 6/4/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/19/2019 | JULIUS GARCIA |
| Sewer availability | Cleared | 6/19/2019 | ROSE MARIE SMITH |
| GPI Written Notices | Cleared | 6/26/2019 | JENNIFER LEE |
| Grading Pre-Inspection | Cleared | 6/26/2019 | JENNIFER LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/4/2019 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/9/2019 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 12/9/2019 | Partial Inspection | PIERRE VEGA |
| Pre-Inspection | 12/3/2020 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/8/2020 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/15/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/11/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/23/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/23/2021 | Approved | MATTHEW NELSON |
| Wood Frame | 2/23/2021 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/1/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/1/2021 | Approved | MATTHEW NELSON |
| Insulation | 3/8/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/8/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/16/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/24/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Final | 11/18/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 11/18/2021 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 11/18/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 12/30/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/30/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/30/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/2/2022 | Approved | MATTHEW NELSON |
| Final | 3/2/2022 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 3/2/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 3/2/2022 | Approved | MATTHEW NELSON |