201 N SALTAIR AVE 90049

Certificate Information: 201 N SALTAIR AVE 90049

Application / Permit
19014-20000-01396
Plan Check / Job No.
B19VN04371
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
24'-11" x 69'-10" IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/25/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 SARKIS HARABEDIAN
Corrections Issued 4/1/2019 SARKIS HARABEDIAN
Quality Review Completed 4/3/2019 OMID HEDAYAT
Building Plans Picked Up 4/8/2019 APPLICANT
Green Plans Picked Up 4/8/2019 APPLICANT
Applicant returned to address corrections 7/12/2019 SARKIS HARABEDIAN
Plan Check Approved 8/20/2019 SARKIS HARABEDIAN
Issued 9/25/2019 LADBS
CofO in Progress 11/18/2021 CARLOS MATAMOROS
CofO in Progress 12/4/2021 CARLOS MATAMOROS
Permit Finaled 12/30/2021 DANIEL ORRANTE
CofO Issued 12/30/2021 DANIEL ORRANTE
Permit Finaled 12/30/2021 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/6/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 5/6/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 5/6/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 5/6/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 5/6/2019 MARKOS PEREZ-BRAN
Green Code Cleared 5/10/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 5/13/2019 GEORGE SUCHAND
Low Impact Development Cleared 7/2/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 7/11/2019 MARKOS PEREZ-BRAN
GPI Written Notices Cleared 7/12/2019 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 7/12/2019 SARKIS HARABEDIAN

Contact Information

Architect Maly,, Farzin; Lic. No.: C33731 7136 HASKELL AVENUE # 320      VAN NUYS, CA 91406
Contractor Trinity Builders & Design Inc; Lic. No.: 988119-B 7022 DARBY AVE UNIT A      RESEDA, CA 91335
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/7/2019 Conditional Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 11/7/2019 Partial Approval ANTHONY MCDOWALL
Special/Order Compliance 11/7/2019 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 11/19/2019 Corrections Issued ANTHONY MCDOWALL
Wood Frame 11/19/2019 Partial Approval ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 11/23/2019 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 2/5/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Approved CARLOS MATAMOROS
Gas Test 5/29/2020 Approved CARLOS MATAMOROS
PLUMBING-Rough 5/29/2020 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 6/2/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 7/23/2020 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 7/23/2020 Not Ready for Inspection CARLOS MATAMOROS
Wood Frame 7/23/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 7/24/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 7/24/2020 Corrections Issued CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/24/2020 Approved CARLOS MATAMOROS
Green Building Rough 7/24/2020 Approved CARLOS MATAMOROS
HVAC-Rough 7/24/2020 Corrections Issued CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/24/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 8/4/2020 Approved CARLOS MATAMOROS
HVAC-Rough 8/4/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/18/2020 Approved CARLOS MATAMOROS
Insulation 10/5/2020 Approved CARLOS MATAMOROS
Shower Pan 10/5/2020 Approved CARLOS MATAMOROS
Drywall Nailing 10/23/2020 Corrections Issued CARLOS MATAMOROS
Drywall Nailing 10/27/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/18/2020 Approved CARLOS MATAMOROS
Sewer 3/22/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Sewer 3/23/2021 Corrections Issued CARLOS MATAMOROS
Sewer 3/31/2021 Approved CARLOS MATAMOROS
Sewer 4/6/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 6/16/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 6/24/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 6/28/2021 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 6/28/2021 Approved CARLOS MATAMOROS
PLUMBING-Final 7/27/2021 Partial Approval CARLOS MATAMOROS
Gas Test 8/19/2021 Approved CARLOS MATAMOROS
PLUMBING-Final 8/19/2021 Approved CARLOS MATAMOROS
HVAC-Final 9/20/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 9/28/2021 Corrections Issued CARLOS MATAMOROS
Final 9/28/2021 Corrections Issued CARLOS MATAMOROS
Green Building Final 9/28/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/28/2021 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/28/2021 Approved CARLOS MATAMOROS
ELECTRICAL-Final 11/9/2021 Approved CARLOS MATAMOROS
Final 11/9/2021 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 11/9/2021 Approved CARLOS MATAMOROS