201 N SALTAIR AVE 90049
Certificate Information: 201 N SALTAIR AVE 90049
- Application / Permit
- 19014-20000-01396
- Plan Check / Job No.
- B19VN04371
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 24'-11" x 69'-10" IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/25/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 4/1/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 4/3/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 4/8/2019 | APPLICANT |
| Green Plans Picked Up | 4/8/2019 | APPLICANT |
| Applicant returned to address corrections | 7/12/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 8/20/2019 | SARKIS HARABEDIAN |
| Issued | 9/25/2019 | LADBS |
| CofO in Progress | 11/18/2021 | CARLOS MATAMOROS |
| CofO in Progress | 12/4/2021 | CARLOS MATAMOROS |
| Permit Finaled | 12/30/2021 | DANIEL ORRANTE |
| CofO Issued | 12/30/2021 | DANIEL ORRANTE |
| Permit Finaled | 12/30/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/6/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 5/6/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 5/6/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 5/6/2019 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 5/10/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 5/13/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 7/2/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/11/2019 | MARKOS PEREZ-BRAN |
| GPI Written Notices | Cleared | 7/12/2019 | SARKIS HARABEDIAN |
| Grading Pre-Inspection | Cleared | 7/12/2019 | SARKIS HARABEDIAN |
Contact Information
| Architect | Maly,, Farzin; Lic. No.: C33731 | 7136 HASKELL AVENUE # 320 VAN NUYS, CA 91406 |
| Contractor | Trinity Builders & Design Inc; Lic. No.: 988119-B | 7022 DARBY AVE UNIT A RESEDA, CA 91335 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/7/2019 | Conditional Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 11/7/2019 | Partial Approval | ANTHONY MCDOWALL |
| Special/Order Compliance | 11/7/2019 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 11/19/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Wood Frame | 11/19/2019 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2019 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/5/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/29/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/29/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 6/2/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/23/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 7/23/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 7/23/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/24/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/24/2020 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 7/24/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 7/24/2020 | Corrections Issued | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 7/24/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/4/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 8/4/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/18/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 10/5/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 10/5/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 10/23/2020 | Corrections Issued | CARLOS MATAMOROS |
| Drywall Nailing | 10/27/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/18/2020 | Approved | CARLOS MATAMOROS |
| Sewer | 3/22/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 3/23/2021 | Corrections Issued | CARLOS MATAMOROS |
| Sewer | 3/31/2021 | Approved | CARLOS MATAMOROS |
| Sewer | 4/6/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/16/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/24/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Service/Power Release | 6/28/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 7/27/2021 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 8/19/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 8/19/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 9/20/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| Final | 9/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 9/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 9/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/28/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/9/2021 | Approved | CARLOS MATAMOROS |
| Final | 11/9/2021 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 11/9/2021 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 11/9/2021 | Approved | CARLOS MATAMOROS |