13915 W LOUVRE ST 91331

Certificate Information: 13915 W LOUVRE ST 91331

Application / Permit
19014-20000-01388
Plan Check / Job No.
B19VN04345
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
17'-4" X 29'-4" ADDITION FOR TWO NEW BEDROOMS AND ONE NEW BATHROOM
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 5/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2019 APPLICANT
Assigned to Plan Check Engineer 3/19/2019 JEROME MAGAT PALMA
Corrections Issued 3/20/2019 JEROME MAGAT PALMA
Building Plans Picked Up 3/26/2019 APPLICANT
Plan Check Approved 4/11/2019 JEROME MAGAT PALMA
Issued 8/5/2020 APPLICANT
CofO in Progress 4/21/2022 MICHEL ABAJAN
CofO Issued 5/14/2022 MICHAEL SMITH
Permit Finaled 5/14/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/11/2019 JOHN LIN
Roof/Waste drainage to street Cleared 4/11/2019 JOHN LIN
Sewer availability Cleared 4/11/2019 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2021 Approved MICHEL ABAJAN
METHANE-Barrier 6/11/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 6/11/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/24/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 6/24/2021 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Rough 6/24/2021 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 6/24/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 6/24/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 7/15/2021 Approved MICHEL ABAJAN
MERV13>=Rough 7/15/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 7/15/2021 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 7/23/2021 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 9/17/2021 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 1/6/2022 Approved MICHEL ABAJAN
Green Building Rough 1/6/2022 Approved MICHEL ABAJAN
Insulation 1/12/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/14/2022 Approved MICHEL ABAJAN
Drywall Nailing 1/20/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/20/2022 Not Ready for Inspection MICHEL ABAJAN
Gas Test 3/30/2022 Not Ready for Inspection DEANDRE HOFFMAN
Final 4/14/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 4/14/2022 Not Ready for Inspection MICHEL ABAJAN
MERV13>=Final 4/14/2022 Approved MICHEL ABAJAN
PLUMBING-Final 4/14/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 4/14/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/19/2022 Approved MICHEL ABAJAN
Final 4/19/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 4/19/2022 Approved MICHEL ABAJAN
HVAC-Final 4/19/2022 Approved MICHEL ABAJAN
Final 4/21/2022 OK to Issue CofO MICHEL ABAJAN