10153 W STAGG ST 91352

Certificate Information: 10153 W STAGG ST 91352

Application / Permit
19014-20000-01298
Plan Check / Job No.
B19VN04073
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Relocate garage entrance, add 21.5' x 24.5' to the front of dwelling for new living room, 1/2 bathroom and 3/4 bathroom per design.
Permit Issued
Issued on 4/16/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2019 APPLICANT
Assigned to Plan Check Engineer 3/14/2019 ALDOUS CHIC
Corrections Issued 3/14/2019 ALDOUS CHIC
Plan Check Approved 4/12/2019 NIKTA MOUSAVI
Issued 4/16/2019 LADBS
CofO in Progress 3/18/2020 BEAU COLLINS
CofO Issued 5/19/2020 MICHAEL SMITH
Permit Finaled 5/19/2020 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 4/9/2019 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 4/11/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 4/11/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/1/2019 Approved MATTHEW NELSON
Grounding or Bonding 5/1/2019 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/9/2019 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 6/7/2019 Partial Approval BEAU COLLINS
ELECTRICAL-Rough 6/10/2019 Approved MATTHEW NELSON
Green Building Rough 6/10/2019 Approved MATTHEW NELSON
MERV13>=Rough 6/10/2019 Not Ready for Inspection MATTHEW NELSON
Insulation 6/18/2019 Partial Approval BEAU COLLINS
Interior/Exterior Lathing 6/18/2019 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 6/20/2019 Approved BEAU COLLINS
Green Building Rough 6/20/2019 Approved BEAU COLLINS
Insulation 6/20/2019 Approved BEAU COLLINS
Interior/Exterior Lathing 6/20/2019 Approved BEAU COLLINS
MERV13>=Rough 6/20/2019 Approved BEAU COLLINS
Drywall Nailing 10/17/2019 Approved BEAU COLLINS
ELECTRICAL-Final 10/17/2019 Approved BEAU COLLINS
Final 10/17/2019 Corrections Issued BEAU COLLINS
Green Building Final 10/17/2019 Not Ready for Inspection BEAU COLLINS
HVAC-Final 10/17/2019 Not Ready for Inspection BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 10/17/2019 SGSOV Approved BEAU COLLINS
Smoke Detectors 10/17/2019 Approved BEAU COLLINS
ELECTRICAL-Final 3/16/2020 Not Ready for Inspection JOHN HAYES
Final 3/16/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 3/16/2020 Not Ready for Inspection JOHN HAYES
HVAC-Final 3/16/2020 Not Ready for Inspection JOHN HAYES
MERV13>=Final 3/16/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 3/16/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 3/17/2020 Approved BEAU COLLINS
HVAC-Final 3/17/2020 Approved BEAU COLLINS
Final 3/18/2020 OK to Issue CofO BEAU COLLINS
Green Building Final 3/18/2020 Approved BEAU COLLINS
MERV13>=Final 3/18/2020 Approved BEAU COLLINS