10556 1/2 W LANARK ST 91352
Certificate Information: 10556 1/2 W LANARK ST 91352
- Application / Permit
- 19014-20000-01287
- Plan Check / Job No.
- B19VN04043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING 1-STORY TYPE VB DETACHED 2-CAR GARAGE INTO ACCESSORY DWELLIING UNIT PER AB 494 AND SB 229, AND ADDITION OF 175 SQ. FT.
- Permit Issued
- Issued on 2/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 3/13/2019 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 3/18/2019 | APPLICANT |
| Applicant returned to address corrections | 11/19/2019 | SERGIO SILVA |
| Plan Check Approved | 11/22/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 2/11/2020 | LADBS |
| CofO in Progress | 9/1/2022 | DAVID ANDERSON |
| Permit Finaled | 9/7/2022 | MICHAEL SMITH |
| CofO Issued | 9/7/2022 | MICHAEL SMITH |
| Permit Finaled | 9/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 4/18/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/18/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 10/18/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/18/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/21/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/30/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 12/3/2020 | Not Ready for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 2/9/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Rough | 2/9/2021 | Not Ready for Inspection | BEAU COLLINS |
| Wood Frame | 5/20/2021 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 7/28/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Rough | 7/28/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 8/9/2021 | Corrections Issued | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 10/6/2021 | Partial Inspection | WILLIAM KUEHN |
| Interior/Exterior Lathing | 11/2/2021 | Approved | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 11/2/2021 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 4/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/14/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/14/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/14/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/14/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/14/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/14/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 8/3/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 8/3/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 8/3/2022 | Approved | DAVID ANDERSON |
| Final | 8/24/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 8/31/2022 | OK to Issue CofO | DAVID ANDERSON |