16803 W GRESHAM ST 91343
Certificate Information: 16803 W GRESHAM ST 91343
- Application / Permit
- 19014-20000-01263
- Plan Check / Job No.
- B19VN03975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION OF MASTER BEDROOM, BATHROOM, FAMILY ROOM (IRR 18'-10" X 29'-5") OVER (E) GARAGE TO (E) 2-STORY SFD W/ ATTACHED GARAGE; DEMO REAR PATIO COVER (18' X 13') & ADD (N) PATIO COVER (22'-6" X 8'-6") WITH DECK ABOVE (22'-6" X 8'-6"); INTERIOR REMODEL
- Permit Issued
- Issued on 8/15/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 4/8/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 4/10/2019 | STEVEN KIM |
| Building Plans Picked Up | 4/10/2019 | APPLICANT |
| Green Plans Picked Up | 4/17/2019 | APPLICANT |
| Plan Check Approved | 8/1/2019 | NILOOFAR MEHRAIN |
| Issued | 8/15/2019 | LADBS |
| CofO in Progress | 8/31/2020 | MICHAEL TEMPLE |
| CofO Issued | 9/10/2020 | MICHAEL SMITH |
| Permit Finaled | 9/10/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/9/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/9/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 7/11/2019 | MICHAEL AYERS |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 1/23/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 1/23/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/12/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/12/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 2/12/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 2/12/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/18/2020 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2020 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 2/18/2020 | Approved | JACK KARGODORIAN |
| Deputy Steel/Welding | 2/26/2020 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/26/2020 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 2/26/2020 | Approved | JACK KARGODORIAN |
| Wood Frame | 2/26/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Reinf. Concrete | 2/28/2020 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 2/28/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 2/28/2020 | Approved | JACK KARGODORIAN |
| Insulation | 3/4/2020 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/4/2020 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 3/4/2020 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 3/5/2020 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 3/11/2020 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 6/23/2020 | Approved | MATTHEW NELSON |
| Final | 6/23/2020 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/23/2020 | Approved | MATTHEW NELSON |
| Green Building Final | 6/23/2020 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 6/23/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/23/2020 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 6/23/2020 | Approved | MATTHEW NELSON |
| Final | 6/26/2020 | OK to Issue CofO | DANIEL ORRANTE |
| Green Building Final | 6/26/2020 | Approved | DANIEL ORRANTE |