19261 W BERNETTA PL 91356
Certificate Information: 19261 W BERNETTA PL 91356
- Application / Permit
- 19014-20000-01246
- Plan Check / Job No.
- B19VN03923
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodeling to re-frame entire roof, enclose 21'3" x 5'7" breezeway, remove majority of interior and reconfigure with additions of irregular shapes 46'11" x 14'8" & 69.5' x 13.25'. All works are per design
- Permit Issued
- Issued on 8/29/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2019 | ALDOUS CHIC |
| Corrections Issued | 3/26/2019 | ALDOUS CHIC |
| Quality Review Completed | 3/26/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 3/28/2019 | APPLICANT |
| Green Plans Picked Up | 3/28/2019 | APPLICANT |
| Plan Check Approved | 8/27/2019 | ALDOUS CHIC |
| Issued | 8/29/2019 | LADBS |
| CofO in Progress | 6/22/2021 | DAVID SANDOVAL |
| CofO Issued | 6/26/2021 | MICHAEL SMITH |
| Permit Finaled | 6/26/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/13/2019 | ALDOUS CHIC |
| GPI Written Notices | Cleared | 3/24/2019 | ALDOUS CHIC |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2019 | JOHN LIN |
| Sewer availability | Cleared | 4/16/2019 | JOHN LIN |
| Construction near power lines | Cleared | 7/28/2019 | RIDWAN HARDY |
| Green Code | Cleared | 8/22/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 8/22/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/22/2019 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: C38991 | 25531 PRADO DELASBELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/15/2019 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 12/16/2019 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 12/17/2019 | Partial Approval | SEAN WIRCH |
| PLUMBING-Rough | 1/8/2020 | Corrections Issued | RONALD COWAN |
| PLUMBING-Rough | 1/9/2020 | Partial Approval | SEAN WIRCH |
| Pre-Inspection | 1/9/2020 | Corrections Issued | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Approved | DAVID SANDOVAL |
| Green Building Rough | 3/6/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/9/2020 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 6/9/2020 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 6/9/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 6/9/2020 | Partial Approval | DAVID SANDOVAL |
| Insulation | 6/16/2020 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 6/22/2020 | Approved | STEVEN BACK |
| Shower Pan | 8/6/2020 | Partial Approval | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/10/2020 | Approved | DAVID SANDOVAL |
| Shower Pan | 8/10/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 3/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 3/3/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 3/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Final | 3/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 3/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/3/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 3/3/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 6/9/2021 | Approved | DAVID SANDOVAL |
| Final | 6/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Gas Test | 6/9/2021 | Approved | DAVID SANDOVAL |
| Green Building Final | 6/9/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 6/16/2021 | Partial Approval | DAVID SANDOVAL |
| Green Building Final | 6/16/2021 | Approved | DAVID SANDOVAL |
| HVAC-Final | 6/16/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 6/16/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 6/16/2021 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 6/16/2021 | Approved | DAVID SANDOVAL |
| Final | 6/22/2021 | OK to Issue CofO | DAVID SANDOVAL |
| Service/Power Release | 6/22/2021 | Approved | DAVID SANDOVAL |