19261 W BERNETTA PL 91356

Certificate Information: 19261 W BERNETTA PL 91356

Application / Permit
19014-20000-01246
Plan Check / Job No.
B19VN03923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodeling to re-frame entire roof, enclose 21'3" x 5'7" breezeway, remove majority of interior and reconfigure with additions of irregular shapes 46'11" x 14'8" & 69.5' x 13.25'. All works are per design
Permit Issued
Issued on 8/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 ALDOUS CHIC
Corrections Issued 3/26/2019 ALDOUS CHIC
Quality Review Completed 3/26/2019 ABDUL CHEGENI
Building Plans Picked Up 3/28/2019 APPLICANT
Green Plans Picked Up 3/28/2019 APPLICANT
Plan Check Approved 8/27/2019 ALDOUS CHIC
Issued 8/29/2019 LADBS
CofO in Progress 6/22/2021 DAVID SANDOVAL
CofO Issued 6/26/2021 MICHAEL SMITH
Permit Finaled 6/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/13/2019 ALDOUS CHIC
GPI Written Notices Cleared 3/24/2019 ALDOUS CHIC
Eng Process Fee Ord 176,300 Cleared 4/16/2019 JOHN LIN
Sewer availability Cleared 4/16/2019 JOHN LIN
Construction near power lines Cleared 7/28/2019 RIDWAN HARDY
Green Code Cleared 8/22/2019 DAVID MATSON
Low Impact Development Cleared 8/22/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/22/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: C38991 25531 PRADO DELASBELLOTAS      CALABASAS, CA 91302

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/15/2019 Approved SEAN WIRCH
Footing/Foundation/Slab 12/16/2019 Approved SEAN WIRCH
Deputy Reinf. Concrete 12/17/2019 Partial Approval SEAN WIRCH
PLUMBING-Rough 1/8/2020 Corrections Issued RONALD COWAN
PLUMBING-Rough 1/9/2020 Partial Approval SEAN WIRCH
Pre-Inspection 1/9/2020 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Approved DAVID SANDOVAL
Green Building Rough 3/6/2020 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 6/9/2020 Approved DAVID SANDOVAL
ELECTRICAL-Rough 6/9/2020 Partial Approval DAVID SANDOVAL
Green Building Rough 6/9/2020 Approved DAVID SANDOVAL
HVAC-Rough 6/9/2020 Approved DAVID SANDOVAL
PLUMBING-Rough 6/9/2020 Partial Approval DAVID SANDOVAL
Insulation 6/16/2020 Approved DAVID SANDOVAL
Drywall Nailing 6/22/2020 Approved STEVEN BACK
Shower Pan 8/6/2020 Partial Approval DAVID SANDOVAL
Interior/Exterior Lathing 8/10/2020 Approved DAVID SANDOVAL
Shower Pan 8/10/2020 Approved DAVID SANDOVAL
ELECTRICAL-Final 3/3/2021 Not Ready for Inspection DAVID SANDOVAL
Final 3/3/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 3/3/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 3/3/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 3/3/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/3/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 3/3/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 6/9/2021 Approved DAVID SANDOVAL
Final 6/9/2021 Not Ready for Inspection DAVID SANDOVAL
Gas Test 6/9/2021 Approved DAVID SANDOVAL
Green Building Final 6/9/2021 Not Ready for Inspection DAVID SANDOVAL
Final 6/16/2021 Partial Approval DAVID SANDOVAL
Green Building Final 6/16/2021 Approved DAVID SANDOVAL
HVAC-Final 6/16/2021 Approved DAVID SANDOVAL
PLUMBING-Final 6/16/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/16/2021 SGSOV Approved DAVID SANDOVAL
Service/Power Release 6/16/2021 Approved DAVID SANDOVAL
Final 6/22/2021 OK to Issue CofO DAVID SANDOVAL
Service/Power Release 6/22/2021 Approved DAVID SANDOVAL