7059-7061 N COSTELLO AVE 91405

Certificate Information: 7059-7061 N COSTELLO AVE 91405

Application / Permit
19014-20000-01231
Plan Check / Job No.
B19VN03876
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 15'-7" X 33'-10" ADDITION TO (E) SFD OF (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 . ALL WORK PER WFPP
Permit Issued
Issued on 3/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2019 APPLICANT
Assigned to Plan Check Engineer 3/12/2019 SELLA BENYAMIN
Plan Check Approved 3/12/2019 RARES BODEA
Issued 3/12/2019 LADBS
CofO in Progress 1/24/2023 RYAN SALAZAR
Permit Finaled 2/13/2023 MICHAEL SMITH
CofO Issued 2/13/2023 MICHAEL SMITH
Permit Finaled 2/13/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/12/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/12/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/12/2019 LEE GUILBEAUX
Sewer availability Cleared 3/12/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Approved MISAEL ESPARZA
Deck 5/5/2020 Not Ready for Inspection MISAEL ESPARZA
Sewer 5/5/2020 Approved MISAEL ESPARZA
Wood Frame 5/5/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 12/21/2020 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 12/21/2020 Partial Inspection DAVID MATSON
Green Building Rough 12/21/2020 Not Ready for Inspection DAVID MATSON
Light Gage Steel Frame 12/21/2020 Approved DAVID MATSON
PLUMBING-Rough 12/21/2020 Not Ready for Inspection DAVID MATSON
Reinforced Concrete Frame 12/21/2020 Approved DAVID MATSON
Reinforced Masonry Frame 12/21/2020 Approved DAVID MATSON
Structural Steel Frame 12/21/2020 Approved DAVID MATSON
Wood Frame 12/21/2020 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 1/5/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/5/2021 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 1/5/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 1/5/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/7/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 1/7/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 1/7/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/7/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/12/2021 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 4/12/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval MICHEL ABAJAN
Gas Test 4/12/2021 Approved MICHEL ABAJAN
Green Building Rough 4/12/2021 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 4/12/2021 Approved MICHEL ABAJAN
Underground Mechanical 4/12/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 5/28/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Approved JENNIFER RABUCHIN
Green Building Rough 5/28/2021 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 5/28/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 5/28/2021 Approved JENNIFER RABUCHIN
Insulation 7/19/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 7/19/2021 Partial Approval ALAN MORELOS
Drywall Nailing 8/20/2021 Approved AMY COLIN
Interior/Exterior Lathing 8/20/2021 Approved AMY COLIN
Shower Pan 8/20/2021 Approved AMY COLIN
BUILDING-Rough-Frame 3/10/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/10/2022 Corrections Issued JENNIFER RABUCHIN
Final 3/10/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/10/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 3/10/2022 Approved JENNIFER RABUCHIN
HVAC-Final 3/10/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 3/10/2022 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 3/10/2022 Corrections Issued JENNIFER RABUCHIN
Final 10/5/2022 Corrections Issued RICHARD DOCKUS
Green Building Final 10/5/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready RICHARD DOCKUS
Smoke Detectors 10/5/2022 Approved RICHARD DOCKUS
Final 10/13/2022 Corrections Issued ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 10/13/2022 SGSOV Not Ready ROBERT GOLD
Final 11/18/2022 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 11/18/2022 SGSOV Approved ROBERT GOLD
Final 11/23/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Final 1/24/2023 Approved RYAN SALAZAR
Final 1/24/2023 OK to Issue CofO RYAN SALAZAR
HVAC-Final 1/24/2023 Approved RYAN SALAZAR
PLUMBING-Final 1/24/2023 Approved RYAN SALAZAR