11481 N JEFF AVE 91342
Certificate Information: 11481 N JEFF AVE 91342
- Application / Permit
- 19014-20000-01064
- Plan Check / Job No.
- B19VN03373
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 36' 3" X 19' 2ND STORY ADDITION ABOVE (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 11/14/2020
- Issuing Office
- Current Status
- Issued on 11/14/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 4/9/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 4/11/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 4/12/2019 | APPLICANT |
| Green Plans Picked Up | 4/12/2019 | APPLICANT |
| Plan Check Approved | 10/16/2019 | GURUNATH NESARAJAH |
| Issued | 11/14/2020 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/15/2019 | VICKY TAVITIAN |
| ZI | Cleared | 7/15/2019 | VICKY TAVITIAN |
| Low Impact Development | Cleared | 9/27/2019 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2019 | JULIUS GARCIA |
| Green Code | Cleared | 10/3/2019 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 10/3/2019 | JULIUS GARCIA |
| Sewer availability | Cleared | 10/3/2019 | JULIUS GARCIA |
| Grading Pre-Inspection | Cleared | 10/11/2019 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2020 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 12/11/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/25/2021 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 1/25/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 1/25/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/2/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 2/2/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/5/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 2/5/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/9/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/9/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 2/18/2021 | Approved | MATTHEW NELSON |
| Insulation | 2/22/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 2/26/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 3/23/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/30/2021 | Approved | MATTHEW NELSON |