11320 N TAMARACK AVE 91340
Certificate Information: 11320 N TAMARACK AVE 91340
- Application / Permit
- 19014-20000-01058
- Plan Check / Job No.
- B19VN03354
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 16'X42' TWO STORY ADDITION TO REAR OF (E) ONE STORYSFD WITH ATTACHED CARPORT
- Permit Issued
- Issued on 10/19/2020
- Issuing Office
- Metro
- Current Status
- Issued on 10/19/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | DAWN MC NULTY |
| Green Plans Picked Up | 4/8/2019 | APPLICANT |
| Corrections Issued | 4/17/2019 | DAWN MC NULTY |
| Quality Review Completed | 4/17/2019 | STEVEN KIM |
| Building Plans Picked Up | 4/18/2019 | APPLICANT |
| Plan Check Approved | 9/27/2020 | DAWN MC NULTY |
| Issued | 10/19/2020 | APPLICANT |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 4/16/2020 | LAUREN PADICK |
| Permit | Cleared | 4/16/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/22/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 6/10/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 8/24/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/3/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Francisco Javier; Lic. No.: S5126 | 199 E THOUSAND OAKS BLVD STE 206 THOUSAND OAKS, CA 91360 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/6/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 4/6/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 4/6/2021 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 9/21/2021 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 10/4/2021 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/10/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/4/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 4/4/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Rough | 4/4/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 4/4/2022 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 5/19/2022 | No Access for Inspection | JENNIFER RABUCHIN |
| Insulation | 6/1/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Wood Frame | 6/1/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/5/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/17/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/7/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/16/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/13/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/19/2023 | Approved | JOHN COLEMAN |
| Final | 8/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/7/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/7/2024 | Approved | JENNIFER RABUCHIN |
| Final | 8/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/12/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |