14519 W RYAN ST 91342

Certificate Information: 14519 W RYAN ST 91342

Application / Permit
19014-20000-00948
Plan Check / Job No.
B19VN03015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW IRR. ADDITIONS: 16'-11" X 34'-5" & 40'-8" X 32'-6" TO (E) 1-STORY SFD, ALSO ADD (N) ATT. 21'-0" X 22'-7", 2-CAR GARAGE & (10'-0" X 7.25) ATT. PORCH; AND REMODEL TO (E) SFD. [SEE COMMENTS] <SPRINKLERS REQ'D THROUGHOUT>
Permit Issued
Issued on 2/20/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/26/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 ALEXANDER SBARDELLATI
Corrections Issued 3/29/2019 ALEXANDER SBARDELLATI
Green Plans Picked Up 4/2/2019 APPLICANT
Quality Review Completed 4/4/2019 STEVEN KIM
Building Plans Picked Up 4/5/2019 APPLICANT
Applicant returned to address corrections 9/17/2019 ABDUL CHEGENI
Plan Check Approved 11/5/2019 ABDUL CHEGENI
Issued 2/20/2020 LADBS
CofO in Progress 10/23/2025 KEVIN BERBERYAN
Permit Finaled 10/31/2025 RUBEN SALAS
CofO Issued 10/31/2025 RUBEN SALAS
Permit Finaled 10/31/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 5/3/2019 JOHN LIN
Tract Map conditions Cleared 5/3/2019 STEVEN WECHSLER
Green Code Cleared 8/14/2019 MICHAEL AYERS
Roof/Waste drainage to street Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 8/27/2019 MITESH PATEL
Sewer availability Cleared 8/27/2019 APEKSHYA BAJRACHARYA
Miscellaneous Cleared 8/28/2019 MARC WOERSCHING
Trees in Parkway Cleared 8/28/2019 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 9/4/2019 GABRIEL ROBLES

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/29/2022 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 1/8/2024 Approved KEVIN BERBERYAN
Deputy Drilled-In Anchors 1/9/2024 Conditional Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 1/29/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 1/31/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 2/7/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 4/5/2024 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 4/5/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 4/5/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 4/12/2024 Approved KEVIN BERBERYAN
HVAC-Rough 4/12/2024 Approved KEVIN BERBERYAN
Service/Power Release 4/12/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 4/19/2024 Corrections Issued DAVID ANDERSON
Green Building Rough 4/19/2024 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 4/30/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 4/30/2024 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 5/15/2024 Partial Approval KEVIN BERBERYAN
Insulation 5/23/2024 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 5/23/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/28/2024 Not Ready for Inspection KEVIN BERBERYAN
Shower Pan 5/28/2024 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 5/30/2024 Approved KEVIN BERBERYAN
Shower Pan 5/30/2024 Approved KEVIN BERBERYAN
Drywall Nailing 6/4/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 6/4/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/4/2024 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 9/4/2024 Not Ready for Inspection MISAEL ESPARZA
Final 9/4/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 9/4/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 9/4/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/30/2024 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 10/30/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 10/30/2024 Not Ready for Inspection KEVIN BERBERYAN
Final 10/30/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 10/30/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 10/30/2024 Conditional Approval KEVIN BERBERYAN
PLUMBING-Final 10/30/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 10/30/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Final 11/6/2024 Approved KEVIN BERBERYAN
HVAC-Final 11/6/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 11/6/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 1/24/2025 Not Ready for Inspection RUBEN SALAS
Final 1/24/2025 Not Ready for Inspection RUBEN SALAS
Green Building Final 1/24/2025 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 1/24/2025 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Not Ready RUBEN SALAS
Service/Power Release 1/24/2025 Not Ready for Inspection RUBEN SALAS
Green Building Final 2/14/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 4/7/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 4/7/2025 Approved GAREN HAYRAPETYAN
Final 4/7/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 4/7/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 4/7/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 4/7/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/15/2025 Partial Approval KEVIN BERBERYAN
Final 4/15/2025 Partial Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 10/23/2025 Approved KEVIN BERBERYAN
Final 10/23/2025 OK to Issue CofO KEVIN BERBERYAN