20332 W CLARK ST 91367
Certificate Information: 20332 W CLARK ST 91367
- Application / Permit
- 19014-20000-00936
- Plan Check / Job No.
- B19VN02971
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 10'-1" x 19' ADDITION TO EXTEND (E) MASTER BEDROOM AND CONVERT PORTION OF (E) GARAGE INTO A (N) BATHROOM AND LAUNDRY ROOM. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 12/5/2020
- Issuing Office
- Current Status
- CofO Corrected on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2019 | NIKTA MOUSAVI |
| Corrections Issued | 2/26/2019 | NIKTA MOUSAVI |
| Applicant returned to address corrections | 8/6/2019 | PINANK PATEL |
| Plan Check Approved | 12/4/2020 | PINANK PATEL |
| Issued | 12/5/2020 | APPLICANT |
| CofO in Progress | 12/17/2021 | STEVEN BACK |
| CofO Issued-Status Void | 9/21/2022 | JOHN JANSON |
| Permit Finaled-Status Void | 9/21/2022 | JOHN JANSON |
| Re-Activate Permit | 9/22/2022 | JOHN JANSON |
| CofO Corrected | 9/22/2022 | JOHN JANSON |
| Permit Finaled | 9/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2019 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 8/6/2019 | PINANK PATEL |
| Roof/Waste drainage to street | Cleared | 8/6/2019 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/18/2021 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 3/23/2021 | Approved | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Corrections Issued | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 4/26/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/25/2021 | Not Ready for Inspection | HENRY KIM |
| Footing/Foundation/Slab | 5/25/2021 | Partial Approval | HENRY KIM |
| PLUMBING-Rough | 5/25/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 6/9/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 6/9/2021 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 6/9/2021 | Not Ready for Inspection | HENRY KIM |
| MERV13>=Rough | 6/9/2021 | Not Ready for Inspection | HENRY KIM |
| PLUMBING-Rough | 6/9/2021 | Corrections Issued | HENRY KIM |
| Shower Pan | 6/24/2021 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 6/29/2021 | Not Ready for Inspection | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 6/29/2021 | Not Ready for Inspection | HENRY KIM |
| Interior/Exterior Lathing | 6/29/2021 | Approved | HENRY KIM |
| MERV13>=Rough | 6/29/2021 | Not Ready for Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 7/15/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 7/15/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2021 | Approved | HENRY KIM |
| Green Building Rough | 7/15/2021 | Not Ready for Inspection | HENRY KIM |
| Deputy Wood Construction | 7/16/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Insulation | 7/26/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/26/2021 | Corrections Issued | RYAN SALAZAR |
| Pre-Inspection | 7/26/2021 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 7/26/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/29/2021 | Approved | HENRY KIM |
| Drywall Nailing | 7/29/2021 | Corrections Issued | HENRY KIM |
| Green Building Rough | 7/29/2021 | Approved | HENRY KIM |
| HVAC-Rough | 7/29/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/29/2021 | Approved | HENRY KIM |
| MERV13>=Rough | 7/29/2021 | Approved | HENRY KIM |
| Drywall Nailing | 8/2/2021 | Approved | ASHLEY THOMPSON |
| Final | 11/15/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 11/15/2021 | Approved | STEVEN BACK |
| Green Building Final | 11/15/2021 | Approved | STEVEN BACK |
| MERV13>=Final | 11/15/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 11/15/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 11/24/2021 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 11/24/2021 | Approved | STEVEN BACK |
| Final | 12/17/2021 | OK to Issue CofO | STEVEN BACK |