4107 N TROOST AVE 91604

Certificate Information: 4107 N TROOST AVE 91604

Application / Permit
19014-20000-00923
Plan Check / Job No.
B19VN02936
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY IRREGULAR ADDITIONS TO (E) 2-ST0RY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
Permit Issued
Issued on 8/21/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2019 APPLICANT
Assigned to Plan Check Engineer 3/7/2019 NILOOFAR MEHRAIN
Corrections Issued 3/11/2019 NILOOFAR MEHRAIN
Quality Review Completed 3/14/2019 CHON CHIO KUO
Building Plans Picked Up 3/14/2019 APPLICANT
Green Plans Picked Up 3/14/2019 APPLICANT
Applicant returned to address corrections 7/3/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 7/29/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/15/2019 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/19/2019 NILOOFAR MEHRAIN
Plan Check Approved 8/20/2019 NILOOFAR MEHRAIN
Issued 8/21/2019 LADBS
CofO in Progress 2/6/2023 JACK KARGODORIAN
No Progress 4/1/2023 MICHAEL PELHAM
CofO in Progress 5/8/2023 JACK KARGODORIAN
Permit Finaled 5/8/2023 MICHAEL SMITH
CofO Issued 5/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 3/21/2019 SHEILA GERSHON
Miscellaneous Cleared 3/21/2019 SHEILA GERSHON
ZI Cleared 3/21/2019 SHEILA GERSHON
Eng Process Fee Ord 176,300 Cleared 6/27/2019 SAFA JAVANMARDI
Sewer availability Cleared 6/27/2019 SAFA JAVANMARDI
Hydrant and Access approval Cleared 7/8/2019 GEORGE SUCHAND
Green Code Cleared 8/14/2019 PARISA ZAHABI
Low Impact Development Cleared 8/14/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/15/2019 GABRIEL ROBLES

Contact Information

Contractor L B Contractors & Company Inc; Lic. No.: 924955-B 5404 WHITTSETT AVE #89      VALLEY VILLAGE, CA 91607
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2019 Approved JEFFREY PARD
PLUMBING-Rough 1/9/2020 Partial Approval JEFFREY PARD
Wood Frame 1/14/2020 Partial Approval JEFFREY PARD
Wood Frame 1/16/2020 Partial Approval JEFFREY PARD
Wood Frame 1/30/2020 Partial Approval JEFFREY PARD
Pre-Inspection 2/24/2020 Partial Approval JEFFREY PARD
Pre-Inspection 6/3/2020 Partial Approval JEFFREY PARD
Deputy Wood Construction 6/15/2020 No Access for Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 6/18/2020 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 6/18/2020 Partial Approval BEAU COLLINS
Pre-Inspection 12/1/2020 Partial Inspection THOMAS FINNILA
Interior/Exterior Lathing 3/17/2021 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 7/12/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 7/12/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 7/21/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 7/30/2021 Approved ARAM AVEDISIAN
HVAC-Rough 8/10/2021 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 8/20/2021 Conditional Approval THOMAS FINNILA
Green Building Rough 8/20/2021 Approved THOMAS FINNILA
HVAC-Rough 8/20/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 9/9/2021 Approved THOMAS FINNILA
Insulation 9/9/2021 Conditional Approval THOMAS FINNILA
Deputy Wood Construction 9/27/2021 Conditional Approval THOMAS FINNILA
Drywall Nailing 11/3/2021 Approved THOMAS FINNILA
Shower Pan 11/3/2021 Partial Inspection THOMAS FINNILA
Shower Pan 12/27/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 1/27/2022 Approved CALEB MEISTER
Wood Frame 5/18/2022 Partial Approval THOMAS FINNILA
Wood Frame 7/8/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Final 12/19/2022 Not Ready for Inspection JACK KARGODORIAN
Service/Power Release 12/19/2022 Not Ready for Inspection JACK KARGODORIAN
Enclosure/Fence 12/30/2022 Not Ready for Inspection JACK KARGODORIAN
Gas Test 12/30/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 2/1/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 2/6/2023 Approved JACK KARGODORIAN
Final 2/6/2023 OK to Issue CofO JACK KARGODORIAN
Green Building Final 2/6/2023 Approved JACK KARGODORIAN
HVAC-Final 2/6/2023 Approved JACK KARGODORIAN
PLUMBING-Final 2/6/2023 Approved JACK KARGODORIAN
Smoke Detectors 2/6/2023 Approved JACK KARGODORIAN
Pre-Inspection 3/31/2023 Corrections Issued JACK KARGODORIAN