2761 S TILDEN AVE 90064

Certificate Information: 2761 S TILDEN AVE 90064

Application / Permit
19014-20000-00685
Plan Check / Job No.
B19VN02147
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) breezeway below 2nd floor for (N) living and bedroom. Convert portion of (E) porch for (N) entry and bath. Add (N) rooftop deck above (E) garage. Add (N) trellis at front of building. Remodel 1st and 2nd floor for (E) single family dwelling
Permit Issued
Issued on 9/5/2020
Issuing Office
Current Status
CofO Issued on 11/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2019 APPLICANT
Assigned to Plan Check Engineer 3/7/2019 ALYSSA N NARCISO
Corrections Issued 3/13/2019 ALYSSA N NARCISO
Green Plans Picked Up 3/13/2019 APPLICANT
Quality Review Completed 3/15/2019 OMID HEDAYAT
Building Plans Picked Up 3/19/2019 APPLICANT
Applicant returned to address corrections 10/11/2019 ALYSSA N NARCISO
Applicant returned to address corrections 10/31/2019 ALYSSA N NARCISO
Applicant returned to address corrections 11/7/2019 ALYSSA N NARCISO
Plan Check Approved 11/27/2019 ALYSSA N NARCISO
Issued 9/5/2020 APPLICANT
CofO in Progress 11/6/2023 JESUS PINEDA
CofO in Progress 11/6/2023 JESUS PINEDA
Permit Finaled 11/8/2023 DANIEL ORRANTE
CofO Issued 11/8/2023 DANIEL ORRANTE
Permit Finaled 11/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/16/2019 GUILLERMO PETRA
Green Code Cleared 10/16/2019 PARISA ZAHABI
Roof/Waste drainage to street Cleared 10/16/2019 GUILLERMO PETRA
Sewer availability Cleared 10/16/2019 GUILLERMO PETRA
Grading Pre-Inspection Cleared 10/17/2019 BARTON HOLMES
Hydrant and Access approval Cleared 10/17/2019 GEORGE SUCHAND
GPI Written Notices Cleared 10/31/2019 ALYSSA N NARCISO
Miscellaneous Cleared 11/7/2019 HERMINIGILDO AGUSTIN

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 1/21/2022 Approved JOHNNY MIRANDA
Deputy Drilled-In Anchors 2/1/2022 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 2/9/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 2/9/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 10/3/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 10/3/2022 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 10/3/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/3/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Partial Approval KENNETH NAGLE
HVAC-Rough 10/11/2022 Approved KENNETH NAGLE
Shower Pan 10/11/2022 Approved KENNETH NAGLE
BUILDING-Rough-Frame 11/17/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 11/17/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 11/17/2022 Not Ready for Inspection JOHNNY MIRANDA
MERV13>=Rough 11/17/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 11/23/2022 Approved JOHNNY MIRANDA
Green Building Rough 11/23/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/23/2022 Partial Approval JOHNNY MIRANDA
MERV13>=Rough 11/23/2022 Approved JOHNNY MIRANDA
Insulation 12/19/2022 Approved KENNETH NAGLE
Drywall Nailing 12/23/2022 Conditional Approval CLAYTON GRAHAM
Drywall Nailing 1/6/2023 Approved CLAYTON GRAHAM
Pre-Inspection 8/10/2023 Partial Inspection JESUS PINEDA
Final 10/26/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/26/2023 Approved JESUS PINEDA
Green Building Final 10/26/2023 Corrections Issued JESUS PINEDA
MERV13>=Final 10/26/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/26/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 10/26/2023 Approved JESUS PINEDA
Final 11/6/2023 OK to Issue CofO JESUS PINEDA
Green Building Final 11/6/2023 Approved JESUS PINEDA