2691 N WALLINGFORD DR 90210

Certificate Information: 2691 N WALLINGFORD DR 90210

Application / Permit
19014-20000-00589
Plan Check / Job No.
B19VN01854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR SHAPED 29'-6" x 4'-10" AND 14'-0" x 28'-8" TO 1ST FLOOR (E) SINGLE FAMILY DWELLING AND 7'-10" x 19'-10" TO 2ND FLOOR (E) SINGLE FAMILY DWELLING. ADD 7'-0" x 5'-9" PORCH.
Permit Issued
Issued on 4/26/2019
Issuing Office
Valley
Current Status
Issued on 4/26/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/5/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 SARKIS HARABEDIAN
Corrections Issued 2/19/2019 SARKIS HARABEDIAN
Quality Review Completed 2/21/2019 OMID HEDAYAT
Building Plans Picked Up 2/26/2019 APPLICANT
Green Plans Picked Up 2/26/2019 APPLICANT
Plan Check Approved 3/21/2019 SARKIS HARABEDIAN
Issued 4/26/2019 LADBS

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/5/2019 ROBERT DUFF
ZA Case Cleared 3/5/2019 ANNA VAN
ZI Cleared 3/5/2019 ANNA VAN
BHO/Hillside ordinance Cleared 3/12/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/12/2019 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/12/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/12/2019 LEE GUILBEAUX
Green Code Cleared 3/12/2019 SARKIS HARABEDIAN
Low Impact Development Cleared 3/12/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/12/2019 LEE GUILBEAUX
Sewer availability Cleared 3/12/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/12/2019 LEE GUILBEAUX
GPI Written Notices Cleared 3/21/2019 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 3/21/2019 SARKIS HARABEDIAN

Contact Information

Contractor Moore Foundations Inc; Lic. No.: 996729-B 7046 DARBY AVE      RESEDA, CA 91335
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/12/2019 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 7/17/2019 Approved CARLOS MATAMOROS
Gas Test 8/20/2019 Approved CARLOS MATAMOROS
Gas Test 9/12/2019 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/12/2019 Approved CARLOS MATAMOROS
Wood Frame 10/7/2019 Approved CARLOS MATAMOROS
Shower Pan 11/13/2019 Approved CARLOS MATAMOROS
Deputy Wood Construction 12/11/2019 Conditional Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 12/12/2019 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 12/12/2019 Approved CARLOS MATAMOROS
Green Building Rough 12/12/2019 Approved CARLOS MATAMOROS
HVAC-Rough 12/12/2019 Approved CARLOS MATAMOROS
PLUMBING-Rough 12/12/2019 Approved CARLOS MATAMOROS
Insulation 12/30/2019 Approved CARLOS MATAMOROS
Drywall Nailing 1/15/2020 Partial Approval ANTHONY MCDOWALL
Drywall Nailing 1/29/2020 Partial Approval ANTHONY MCDOWALL
Insulation 1/29/2020 Partial Approval ANTHONY MCDOWALL
Interior/Exterior Lathing 1/29/2020 Partial Approval ANTHONY MCDOWALL
Drywall Nailing 3/4/2020 Approved ANTHONY MCDOWALL
Shower Pan 3/23/2020 Corrections Issued ANTHONY MCDOWALL
Interior/Exterior Lathing 4/6/2020 Approved ANTHONY MCDOWALL
Shower Pan 4/6/2020 Corrections Issued ANTHONY MCDOWALL
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Approved ANTHONY MCDOWALL
Interior/Exterior Lathing 8/11/2020 Approved ANTHONY MCDOWALL