16902 W HART ST 91406

Certificate Information: 16902 W HART ST 91406

Application / Permit
19014-20000-00521
Plan Check / Job No.
B19VN01616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) (18'-2" x 20'-1") DETACHED GARAGE AND ADD (6' X 18'-2") TO CREATE (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ADD 16'-8" X 18'-1" FOR (N) ATTACHED PATIO COVER. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/3/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 RAPHAEL ROSAS
Corrections Issued 1/31/2019 RAPHAEL ROSAS
Building Plans Picked Up 2/5/2019 APPLICANT
Plan Check Approved 11/22/2019 RAPHAEL ROSAS
Issued 12/3/2019 LADBS
CofO in Progress 6/11/2020 STEVEN BACK
Permit Finaled 6/25/2020 DONALD SUNSERI
CofO Issued 6/25/2020 DONALD SUNSERI
Permit Finaled 6/25/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 2/15/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/15/2019 LEE GUILBEAUX
Sewer availability Cleared 2/15/2019 LEE GUILBEAUX
Construction near power lines Cleared 7/30/2019 RIDWAN HARDY
Roof/Waste drainage to street Cleared 8/8/2019 JULIUS GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/30/2019 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Rough 12/30/2019 Not Ready for Inspection JOSEPH SAGEN
Footing/Foundation/Slab 1/8/2020 Corrections Issued STEVEN BACK
PLUMBING-Rough 1/8/2020 Corrections Issued STEVEN BACK
Sewer 1/8/2020 Approved STEVEN BACK
Deputy Drilled-In Anchors 1/16/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 1/21/2020 Approved STEVEN BACK
Deputy Wood Construction 2/5/2020 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 2/11/2020 Corrections Issued STEVEN BACK
Green Building Rough 2/11/2020 Not Ready for Inspection STEVEN BACK
Rough-Elec/Plmb/HVAC 2/11/2020 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 2/21/2020 Approved STEVEN BACK
Green Building Rough 2/21/2020 Approved STEVEN BACK
Interior/Exterior Lathing 2/21/2020 Partial Approval STEVEN BACK
Rough-Elec/Plmb/HVAC 2/21/2020 Approved STEVEN BACK
Insulation 2/26/2020 Approved STEVEN BACK
Drywall Nailing 3/3/2020 Approved STEVEN BACK
Final 6/4/2020 Corrections Issued STEVEN BACK
Green Building Final 6/4/2020 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/4/2020 SGSOV Approved STEVEN BACK
Smoke Detectors 6/4/2020 Approved STEVEN BACK
Final 6/11/2020 OK to Issue CofO STEVEN BACK
Green Building Final 6/11/2020 Approved STEVEN BACK
Service/Power Release 6/11/2020 Approved STEVEN BACK