5901 N NAGLE AVE 91401
Certificate Information: 5901 N NAGLE AVE 91401
- Application / Permit
- 19014-20000-00318
- Plan Check / Job No.
- B19VN00989
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 36'3" X 52'9" IRREGULAR SHAPED 1ST FLOOR ADDITION TO RELOCATE KITCHEN , FAMILLY ROOM AND LAUNDRY , NEW 2' X 11' ATTACHED PATIO COVER , CONVERT (E) 17'3" X 15'6" 1ST FLOOR W.I.C AND BATHROOM TO RECREATION ROOM AND FULL BATH WITH EXTERIOR ACCESS ACCESSORY TO (E) POOL , NEW 44' X 46' IRREGULAR SHAPED 2ND FLOOR ADDITION TO CREATE (3) NEW BEDROOMS , (3) BATHROOMS, (3) CLOSETS , NEW 16'6" X 18' IRREGULAR SHAPED ATTACHED 2ND FLOOR TRELLIS , REMOVE 16'9" X 3'3" AND 28'9" X 2' FIRST FLOOR PORTIONS OF (E) SFD , INTERIOR REMODEL TO (E) SFD TO REMODEL (2) BEDROOMS . (2) BATHROOMS, CREATE NEW (2) W.I.C., NEW POWDER ROOM , NEW PANTRY, NEW MEDIA AND EQUIPMENT ROOM, NEW 11' X 5' , 5' X 16'6" AND 18' X 16'6" 2ND FLOOR BALCONIES, Re-roof with Class A roof covering material weighing less than 6 pounds per sq. ft. over existing solid sheathing 18 Squares ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | RARES BODEA |
| Corrections Issued | 2/3/2019 | RARES BODEA |
| Quality Review Completed | 2/5/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 2/11/2019 | APPLICANT |
| Green Plans Picked Up | 2/11/2019 | APPLICANT |
| Applicant returned to address corrections | 2/22/2019 | RARES BODEA |
| Plan Check Approved | 4/23/2019 | RARES BODEA |
| Issued | 4/26/2019 | LADBS |
| CofO in Progress | 12/31/2020 | BRENDAN LOONEY |
| Permit Finaled | 4/3/2021 | MICHAEL SMITH |
| CofO Issued | 4/3/2021 | MICHAEL SMITH |
| Permit Finaled | 4/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 3/18/2019 | PARISA ZAHABI |
| Low Impact Development | Cleared | 3/18/2019 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 4/15/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/15/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/11/2019 | Conditional Approval | GREG ALLTON |
| METHANE-Barrier | 7/11/2019 | Approved | GREG ALLTON |
| METHANE-Subgrade | 7/11/2019 | Approved | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2019 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/12/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/16/2019 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/20/2019 | Partial Approval | GREG ALLTON |
| Green Building Rough | 8/20/2019 | Not Ready for Inspection | GREG ALLTON |
| METHANE-Rough | 8/20/2019 | Approved | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2019 | Partial Approval | GREG ALLTON |
| HVAC-Rough | 11/6/2019 | Partial Inspection | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2019 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2019 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2019 | Partial Inspection | GREG ALLTON |
| Deputy Wood Construction | 1/10/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 1/10/2020 | Approved | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2020 | Partial Inspection | ROBERT MINASSIANS |
| PLUMBING-Rough | 1/13/2020 | Corrections Issued | ROBERT MINASSIANS |
| HVAC-Rough | 1/14/2020 | Partial Inspection | GREG ALLTON |
| PLUMBING-Rough | 1/14/2020 | Partial Inspection | GREG ALLTON |
| Shower Pan | 1/21/2020 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 1/24/2020 | Partial Approval | GREG ALLTON |
| HVAC-Rough | 1/31/2020 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 1/31/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Rough | 2/19/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 2/19/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 2/19/2020 | Approved | RAYMOND KEHOE |
| Insulation | 3/2/2020 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 3/4/2020 | Approved | GREG ALLTON |
| Drywall Nailing | 3/18/2020 | Approved | GREG ALLTON |
| Green Building Rough | 3/18/2020 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 12/23/2020 | Approved | BRENDAN LOONEY |
| Final | 12/23/2020 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/23/2020 | Approved | BRENDAN LOONEY |
| Green Building Final | 12/23/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 12/23/2020 | Approved | BRENDAN LOONEY |
| Final | 12/31/2020 | OK to Issue CofO | BRENDAN LOONEY |
| Green Building Final | 12/31/2020 | Approved | BRENDAN LOONEY |