14523 W GREENLEAF ST 91403
Certificate Information: 14523 W GREENLEAF ST 91403
- Application / Permit
- 19014-20000-00263
- Plan Check / Job No.
- B19VN00822
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 10'-0" X 20'-0" ADDITION & CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. "COMPLY WITH DEPARTMENT ORDER effective date 06/18/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/14/2020
- Issuing Office
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 1/17/2019 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 2/4/2019 | APPLICANT |
| Plan Check Approved | 1/27/2020 | ARTIN ZARUKIAN |
| Issued | 5/14/2020 | APPLICANT |
| CofO in Progress | 12/1/2021 | JOEL WILLIAMS |
| Permit Finaled | 12/17/2021 | DANIEL SANCHEZ |
| CofO Issued | 12/17/2021 | DANIEL SANCHEZ |
| Permit Finaled | 12/17/2021 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 3/14/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2019 | JEANIE LAM |
| Sewer availability | Cleared | 3/14/2019 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/27/2019 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 1/4/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 1/27/2020 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Donlong Peter; Lic. No.: S3948 | 8748 E VALLEY BLVD L ROSEMEAD, CA 91770 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2020 | Corrections Issued | GORDON ZUBER |
| Footing/Foundation/Slab | 9/30/2020 | Corrections Issued | GORDON ZUBER |
| Footing/Foundation/Slab | 10/6/2020 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 12/17/2020 | Corrections Issued | GORDON ZUBER |
| Sewer | 12/17/2020 | Partial Approval | GORDON ZUBER |
| Deputy Grading | 12/23/2020 | Approved | GORDON ZUBER |
| Wood Frame | 1/12/2021 | Corrections Issued | GORDON ZUBER |
| Underground Mechanical | 1/21/2021 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 6/9/2021 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 6/9/2021 | Not Ready for Inspection | GORDON ZUBER |
| Green Building Rough | 6/9/2021 | Not Ready for Inspection | GORDON ZUBER |
| PLUMBING-Rough | 6/9/2021 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 7/7/2021 | Corrections Issued | JOEL WILLIAMS |
| ELECTRICAL-Rough | 7/7/2021 | Corrections Issued | JOEL WILLIAMS |
| Green Building Rough | 7/7/2021 | Not Ready for Inspection | JOEL WILLIAMS |
| Interior/Exterior Lathing | 7/12/2021 | Approved | GORDON ZUBER |
| Shower Pan | 7/12/2021 | Approved | GORDON ZUBER |
| ELECTRICAL-Rough | 8/2/2021 | Corrections Issued | GORDON ZUBER |
| Insulation | 8/2/2021 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 8/6/2021 | Approved | GORDON ZUBER |
| PLUMBING-Rough | 8/6/2021 | Approved | GORDON ZUBER |
| Green Building Rough | 8/11/2021 | Approved | GORDON ZUBER |
| HVAC-Rough | 8/11/2021 | Approved | GORDON ZUBER |
| Shower Pan | 9/3/2021 | Not Ready for Inspection | GORDON ZUBER |
| Underground Mechanical | 9/3/2021 | Not Ready for Inspection | GORDON ZUBER |
| Interior/Exterior Lathing | 9/7/2021 | Approved | GORDON ZUBER |
| Shower Pan | 9/7/2021 | Approved | GORDON ZUBER |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | GORDON ZUBER |
| Underground Mechanical | 9/9/2021 | Approved | GORDON ZUBER |
| Drywall Nailing | 11/16/2021 | Approved | GORDON ZUBER |
| Final | 11/16/2021 | Corrections Issued | GORDON ZUBER |
| Green Building Final | 11/16/2021 | Corrections Issued | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | GORDON ZUBER |
| Smoke Detectors | 11/16/2021 | Approved | GORDON ZUBER |
| Final | 11/22/2021 | OK to Issue CofO | GORDON ZUBER |
| Green Building Final | 11/22/2021 | Approved | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Not Ready | GORDON ZUBER |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Approved | ZEYDI STEWART |