304 N CHAUTAUQUA BLVD 90272
Certificate Information: 304 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 19014-20000-00202
- Plan Check / Job No.
- B19VN00664
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. CONVERT (E) TWO-CAR GARAGE TO HABITABLE AREA AND ADD 18'-10" x 25'-2" (N) TWO - CAR CARPORT.
- Permit Issued
- Issued on 8/27/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/7/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 2/15/2019 | SARKIS HARABEDIAN |
| Quality Review Completed | 2/19/2019 | OMID HEDAYAT |
| Green Plans Picked Up | 2/19/2019 | APPLICANT |
| Building Plans Picked Up | 2/21/2019 | APPLICANT |
| Applicant returned to address corrections | 3/12/2019 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 5/7/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 7/12/2019 | SARKIS HARABEDIAN |
| Issued | 8/27/2019 | LADBS |
| CofO in Progress | 7/12/2021 | JOHN KIDWELL |
| CofO Issued | 8/3/2021 | RONALD MYRICK |
| Permit Finaled | 8/3/2021 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 4/17/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 4/17/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 4/17/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2019 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 4/17/2019 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 4/17/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 4/17/2019 | MARKOS PEREZ-BRAN |
| Grading Pre-Inspection | Cleared | 5/7/2019 | SARKIS HARABEDIAN |
| Coastal Zone | Cleared | 6/13/2019 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Hanson Doug Construction; Lic. No.: 872745-B | 19769 HORSESHOE DRIVE TOPANGA, CA 90290 |
| Engineer | Rahbar,, Farzin S; Lic. No.: S2833 | 24372 VANOWEN STREET STE 104 WEST HILLS, CA 91307 |
| Engineer | Stovall,, James Todd; Lic. No.: L7760 | 5840 WEST CRAIG ROAD STE 120-346 LAS VEGAS, NV 89130 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/22/2020 | No Access for Inspection | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 2/20/2020 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 2/20/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| Green Building Rough | 2/20/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| PLUMBING-Rough | 3/3/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| HVAC-Rough | 3/18/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 4/20/2020 | Corrections Issued | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Not Ready for Inspection | MATT KELLERMAN |
| Footing/Foundation/Slab | 4/20/2020 | Not Ready for Inspection | MATT KELLERMAN |
| HVAC-Rough | 4/20/2020 | Not Ready for Inspection | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/21/2020 | Approved | DANNY TOLENTINO |
| HVAC-Rough | 4/21/2020 | Approved | DANNY TOLENTINO |
| Drywall Nailing | 4/24/2020 | Partial Approval | DANNY TOLENTINO |
| Green Building Rough | 4/24/2020 | Partial Approval | DANNY TOLENTINO |
| Insulation | 4/28/2020 | Approved | DANNY TOLENTINO |
| ELECTRICAL-Rough | 8/14/2020 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 8/14/2020 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/19/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/19/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 8/19/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/4/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 11/4/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/4/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/23/2020 | Approved | JOHN KIDWELL |
| Drywall Nailing | 11/23/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 11/23/2020 | Approved | JOHN KIDWELL |
| Final | 7/1/2021 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 7/1/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 7/1/2021 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 7/1/2021 | Approved | JOHN KIDWELL |