607 N RADCLIFFE AVE 90272

Certificate Information: 607 N RADCLIFFE AVE 90272

Application / Permit
19014-20000-00184
Plan Check / Job No.
B19VN00589
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 10'-1" X 18'-2.5" & 5'-5" X 16'-1" IRREGULAR SHAPED ADDITIONS TO (E) & REMODEL (E) SFD FOR (N) BEDROOMS, BATHROOMS, STUDY ROOM, KITCHEN AND DINING ROOM. (N) 12' X 35' IRREGULAR SHAPED ATTACHED DECK AT REAR. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/23/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 RAPHAEL ROSAS
Corrections Issued 1/28/2019 RAPHAEL ROSAS
Quality Review Completed 2/6/2019 STEVEN KIM
Building Plans Picked Up 2/12/2019 APPLICANT
Green Plans Picked Up 2/12/2019 APPLICANT
Applicant returned to address corrections 3/21/2019 RAPHAEL ROSAS
Plan Check Approved 4/4/2019 RAPHAEL ROSAS
Issued 4/23/2019 LADBS
CofO in Progress 9/29/2021 ANDREW NAVE
Permit Finaled 10/25/2021 DANIEL ORRANTE
CofO Issued 10/25/2021 DANIEL ORRANTE
Permit Finaled 10/25/2021 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/22/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 2/22/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 2/22/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 2/22/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 2/22/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/22/2019 APEKSHYA BAJRACHARYA
Distance to fire station Cleared 2/26/2019 ROBERT DUFF
Hydrant and Access approval Cleared 2/26/2019 ROBERT DUFF
Green Code Cleared 3/21/2019 PARISA ZAHABI
Coastal Zone Cleared 4/1/2019 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 4/1/2019 SOPHIE GABEL-SCHEINBAU
ZA Case Cleared 4/1/2019 SOPHIE GABEL-SCHEINBAU
Grading Pre-Inspection Cleared 4/4/2019 RAPHAEL ROSAS

Contact Information

Architect Perella,, Ryan Adam; Lic. No.: C30833 606 N LARCHMONT BLVD # 4A      LOS ANGELES, CA 90004
Contractor Owner-Builder       ,
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/25/2019 Approved ANDREW NAVE
Pre-Inspection 10/24/2019 Corrections Issued MICHAEL TEMPLE
Deputy Reinf. Concrete 3/6/2020 Conditional Approval ANDREW NAVE
Piling/Pier/Caisson 3/11/2020 Partial Inspection ANDREW NAVE
Special/Order Compliance 3/11/2020 Corrections Issued ANDREW NAVE
Deputy Reinf. Concrete 3/12/2020 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 3/12/2020 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 3/12/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 4/7/2020 Corrections Issued ANDREW NAVE
PLUMBING-Rough 4/15/2020 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/27/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 5/27/2020 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 5/28/2020 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 7/27/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 7/30/2020 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 8/3/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 8/5/2020 Approved ANDREW NAVE
Deputy Reinf. Concrete 8/6/2020 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 9/17/2020 Partial Approval ANDREW NAVE
Insulation 9/17/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 9/17/2020 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Partial Approval ANDREW NAVE
BUILDING-Rough-Frame 12/3/2020 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Partial Approval ANDREW NAVE
Verify Sprinkler Sign Off 12/3/2020 Not Ready for Inspection ANDREW NAVE
Deputy Wood Construction 12/9/2020 Approved ROBERT SHELLY
BUILDING-Rough-Frame 12/23/2020 Corrections Issued EVAN COOPER
HVAC-Rough 12/30/2020 Corrections Issued DAVID HEINE
HVAC-Rough 1/19/2021 Partial Inspection ANDREW NAVE
ELECTRICAL-Rough 1/26/2021 Approved ANDREW NAVE
HVAC-Rough 1/28/2021 Approved ANDREW NAVE
PLUMBING-Rough 1/28/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 2/1/2021 Approved ANDREW NAVE
Green Building Rough 2/1/2021 Approved ANDREW NAVE
Verify Sprinkler Sign Off 2/1/2021 Approved ANDREW NAVE
Insulation 2/3/2021 Approved ANDREW NAVE
Drywall Nailing 2/9/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 2/9/2021 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 3/9/2021 Partial Approval ANDREW NAVE
Shower Pan 3/9/2021 Approved ANDREW NAVE
ELECTRICAL-Final 4/21/2021 Corrections Issued ANDREW NAVE
Service/Power Release 4/22/2021 Approved ANDREW NAVE
ELECTRICAL-Final 7/20/2021 Approved ANDREW NAVE
PLUMBING-Final 7/20/2021 Corrections Issued ANDREW NAVE
PLUMBING-Final 7/27/2021 Approved ANDREW NAVE
Final 7/30/2021 Corrections Issued ANDREW NAVE
Green Building Final 7/30/2021 Conditional Approval ANDREW NAVE
HVAC-Final 7/30/2021 Corrections Issued ANDREW NAVE
Final 8/2/2021 Corrections Issued ANDREW NAVE
Green Building Final 8/2/2021 Approved ANDREW NAVE
Final 8/9/2021 Not Ready for Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 8/9/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Final 8/11/2021 Approved ANDREW NAVE
Final 9/29/2021 Conditional Approval ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Approved ANDREW NAVE
Smoke Detectors 9/29/2021 Approved ANDREW NAVE