7040 N FALLBROOK AVE 91307
Certificate Information: 7040 N FALLBROOK AVE 91307
- Application / Permit
- 19014-20000-00179
- Plan Check / Job No.
- B19VN00572
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 19'5" x 25'8" ATTACHED ACCESSORY DWELLING UNIT (WITH ROOF DECK) TO DETACHED GARAGE PER AB 494 AND SB 229. ALL WORKS ARE PER DESIGN
- Permit Issued
- Issued on 3/5/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2019 | APPLICANT |
| Green Plans Picked Up | 1/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | ALDOUS CHIC |
| Corrections Issued | 1/28/2019 | ALDOUS CHIC |
| Quality Review Completed | 1/28/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 1/31/2019 | APPLICANT |
| Plan Check Approved | 2/26/2019 | ALDOUS CHIC |
| Issued | 3/5/2019 | LADBS |
| CofO in Progress | 9/25/2020 | DAVID STEPANYAN |
| CofO Issued | 9/29/2020 | JOHN JANSON |
| Permit Finaled | 9/29/2020 | JOHN JANSON |
Permit Application Clearance Information
| Green Code | Cleared | 1/31/2019 | PARISA ZAHABI |
| Address approval | Cleared | 2/11/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 2/11/2019 | JOHN DALLAS |
| Sewer availability | Cleared | 2/11/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 2/26/2019 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ficinski,, Marek; Lic. No.: S3534 | 4850 N LANTE ST BALDWIN PARK, CA 91706 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/23/2019 | Not Ready for Inspection | PETER FOLLING |
| Sewer | 4/23/2019 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 4/26/2019 | Partial Approval | PETER FOLLING |
| Sewer | 4/26/2019 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 5/17/2019 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2019 | Partial Approval | PETER FOLLING |
| Green Building Rough | 7/17/2019 | Approved | PETER FOLLING |
| PLUMBING-Rough | 7/24/2019 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 8/1/2019 | Not Ready for Inspection | PETER FOLLING |
| Underground Mechanical | 8/1/2019 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 8/16/2019 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 8/23/2019 | Approved | PETER FOLLING |
| Green Building Rough | 8/23/2019 | Approved | PETER FOLLING |
| PLUMBING-Rough | 8/23/2019 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 9/25/2019 | Partial Approval | PETER FOLLING |
| BUILDING-Rough-Frame | 11/25/2019 | Approved | PETER FOLLING |
| HVAC-Rough | 11/25/2019 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 11/25/2019 | Partial Approval | PETER FOLLING |
| Insulation | 12/11/2019 | Approved | PETER FOLLING |
| Drywall Nailing | 12/26/2019 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/26/2020 | Approved | DAVID STEPANYAN |
| Final | 9/15/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 9/15/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 9/15/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Smoke Detectors | 9/15/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 9/24/2020 | Approved | DAVID STEPANYAN |
| Final | 9/24/2020 | OK to Issue CofO | DAVID STEPANYAN |
| PLUMBING-Final | 9/24/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 9/24/2020 | SGSOV Approved | DAVID STEPANYAN |