7420 N RIVERTON AVE 91352

Certificate Information: 7420 N RIVERTON AVE 91352

Application / Permit
19014-20000-00170
Plan Check / Job No.
B19VN00533
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21'-4" X 31'-6" IRREGULAR SHAPED ADDITION TO (E)SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 10/8/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 SARKIS HARABEDIAN
Corrections Issued 2/4/2019 SARKIS HARABEDIAN
Quality Review Completed 2/7/2019 OMID HEDAYAT
Building Plans Picked Up 2/28/2019 APPLICANT
Green Plans Picked Up 2/28/2019 APPLICANT
Applicant returned to address corrections 7/17/2019 SARKIS HARABEDIAN
Plan Check Approved 8/8/2019 SARKIS HARABEDIAN
Issued 10/8/2019 LADBS
CofO in Progress 11/4/2020 DANIEL DREW
Permit Finaled 6/5/2021 MICHAEL SMITH
CofO Issued 6/5/2021 MICHAEL SMITH
Permit Finaled 6/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/5/2019 ISRAEL TAMIRU
Sewer availability Cleared 7/10/2019 CELINA MORENO
Green Code Cleared 7/11/2019 MICHAEL AYERS
Low Impact Development Cleared 7/19/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/22/2019 ELAINE LEI

Contact Information

Contractor Lone Star Renovation & Construction Inc; Lic. No.: 350486-B 15810 GALE AVENUE SUITE 117      HACIENDA HEIGHTS, CA 91745
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2019 Approved GREG ALLTON
Footing/Foundation/Slab 11/6/2019 Approved GREG ALLTON
Floor/Roof Diaphrgm/Shear Wall 12/6/2019 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/6/2019 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 12/12/2019 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 12/12/2019 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 3/12/2020 Approved RAYMOND KEHOE
ELECTRICAL-Rough 3/12/2020 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Partial Approval RAYMOND KEHOE
Green Building Rough 3/12/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 3/12/2020 Approved RAYMOND KEHOE
Insulation 3/31/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/31/2020 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 4/13/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/13/2020 Approved MISAEL ESPARZA
Final 10/26/2020 Corrections Issued DAVID MATSON
Green Building Final 10/26/2020 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Not Ready DAVID MATSON
Smoke Detectors 10/26/2020 Approved DAVID MATSON
ELECTRICAL-Final 11/2/2020 Approved DANIEL DREW
Final 11/2/2020 OK to Issue CofO DANIEL DREW
HVAC-Final 11/2/2020 Approved DANIEL DREW
PLUMBING-Final 11/2/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved DANIEL DREW