542 W CASANOVA ST 90012

Certificate Information: 542 W CASANOVA ST 90012

Application / Permit
19014-20000-00134
Plan Check / Job No.
B19VN00438
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 20'10" x 22'4" family room and irregular shape 32' x 17.5' attached patio cover with roof deck to the rear. All works are per design.
Permit Issued
Issued on 5/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 ALDOUS CHIC
Corrections Issued 1/28/2019 ALDOUS CHIC
Quality Review Completed 1/28/2019 ABDUL CHEGENI
Building Plans Picked Up 1/29/2019 APPLICANT
Green Plans Picked Up 1/29/2019 APPLICANT
Applicant returned to address corrections 5/9/2019 ALDOUS CHIC
Plan Check Approved 5/24/2019 ALDOUS CHIC
Issued 5/29/2019 LADBS
CofO in Progress 3/6/2020 OSVALDO PARAMO
CofO in Progress 3/6/2020 OSVALDO PARAMO
Permit Finaled 3/12/2020 DEROLD HAUFF
CofO Issued 3/12/2020 DEROLD HAUFF
Permit Finaled 3/12/2020 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/8/2016 ALDOUS CHIC
GPI Written Notices Cleared 1/26/2019 ALDOUS CHIC
Hydrant and Access approval Cleared 3/21/2019 GEORGE SUCHAND
Green Code Cleared 4/5/2019 ALDOUS CHIC
Low Impact Development Cleared 4/26/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 5/6/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 5/9/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Mills,, Garrett Ward; Lic. No.: S5271 553 S OAK KNOLL AVE      PASADENA, CA 91101

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2019 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/17/2019 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/23/2019 Approved OSVALDO PARAMO
Deputy Wood Construction 9/24/2019 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 10/8/2019 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/10/2019 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/23/2019 Partial Approval OSVALDO PARAMO
Green Building Rough 10/23/2019 Not Ready for Inspection OSVALDO PARAMO
Insulation 10/23/2019 Partial Approval OSVALDO PARAMO
MERV13>=Rough 10/23/2019 Not Ready for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/28/2019 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 11/29/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 12/16/2019 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 12/16/2019 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/16/2019 Partial Approval OSVALDO PARAMO
Green Building Rough 12/16/2019 Approved OSVALDO PARAMO
MERV13>=Rough 12/16/2019 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 12/23/2019 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 12/23/2019 Partial Inspection RUBEN SALAS
BUILDING-Rough-Frame 12/27/2019 Approved OSVALDO PARAMO
Insulation 1/3/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/9/2020 Approved OSVALDO PARAMO
Drywall Nailing 1/14/2020 Approved OSVALDO PARAMO
Final 2/25/2020 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 2/25/2020 Approved OSVALDO PARAMO
Green Building Final 2/25/2020 Approved OSVALDO PARAMO
MERV13>=Final 2/25/2020 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/25/2020 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 2/25/2020 Approved OSVALDO PARAMO
Final 3/6/2020 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/6/2020 SGSOV Approved OSVALDO PARAMO