5110 W ORANGE PL 90008

Certificate Information: 5110 W ORANGE PL 90008

Application / Permit
19014-10005-05986
Plan Check / Job No.
B24LA04309
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. SUPPLEMENTAL TO PERMIT # 19014-10000-05986 MODIFY FLOOR PLANS AND INCREASE ADDITION. 1 OF 2
Permit Issued
Issued on 7/24/2024
Issuing Office
Current Status
Permit Finaled on 11/19/2025

Permit Application Status History

Submitted 3/8/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 MICHAEL LOPEZ
Corrections Issued 4/5/2024 MICHAEL LOPEZ
Quality Review Completed 4/10/2024 PRANITA SHAH
Applicant returned to address corrections 4/25/2024 STARR CHEN
Applicant returned to address corrections 7/3/2024 MICHAEL LOPEZ
Plan Check Approved 7/16/2024 MICHAEL LOPEZ
No Progress 7/16/2024 MICHAEL LOPEZ
Plan Check Approved 7/16/2024 MICHAEL LOPEZ
Issued 7/24/2024 APPLICANT
Permit Finaled 11/18/2025 LUIS CASTRO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/3/2024 CHRISTINA BRACO
Hydrant and Access approval Cleared 6/1/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 6/5/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 6/5/2024 JEANIE LAM
GPI Written Notices Cleared 7/3/2024 JONATHAN HOM
Grading Pre-Inspection Cleared 7/3/2024 JONATHAN HOM

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Eagle Development & Construction Inc; Lic. No.: 800756-B       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/31/2024 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 8/1/2024 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 8/12/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Partial Approval LUIS CASTRO
Green Building Rough 2/6/2025 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 2/6/2025 Partial Approval LUIS CASTRO
Pre-Inspection 2/6/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Partial Approval LUIS CASTRO
Insulation 2/20/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 2/20/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 3/18/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 3/18/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Approved LUIS CASTRO
Green Building Rough 3/18/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 3/18/2025 Partial Approval LUIS CASTRO
HVAC-Rough 4/3/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 4/3/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 7/24/2025 Approved ANTHONY RAMOS
Gas Test 9/26/2025 Approved MICHAEL LEWIS
Service/Power Release 9/26/2025 Corrections Issued MICHAEL LEWIS
Service/Power Release 10/15/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 11/18/2025 Approved LUIS CASTRO
Final 11/18/2025 Permit Finaled LUIS CASTRO
Green Building Final 11/18/2025 Approved LUIS CASTRO
Green Building Rough 11/18/2025 Approved LUIS CASTRO
Smoke Detectors 11/18/2025 Approved LUIS CASTRO