701 N NIMES ROAD 90077
Certificate Information: 701 N NIMES ROAD 90077
- Application / Permit
- 19014-10004-06529
- Plan Check / Job No.
- B21LA07358
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO 19014-10000-06529 TO REVISE FLOOR PLAN LAYOUT ON EACH LEVEL. NO CHANGE IN SQUARE FOOTAGE OR BUILDING FOOTPRINT.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | KHEDER ALRAZAA |
| Corrections Issued | 4/21/2021 | KHEDER ALRAZAA |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| Applicant returned to address corrections | 6/16/2021 | KHEDER ALRAZAA |
| Plan Check Approved | 6/18/2021 | KHEDER ALRAZAA |
| Issued | 6/22/2021 | APPLICANT |
| Permit Finaled | 6/28/2023 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/25/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 6/25/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 6/25/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | CHRISTOPHER WILSON |
| Wood Frame | 10/28/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2021 | Partial Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 12/22/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 5/11/2022 | Conditional Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 6/28/2023 | Approved | CHRISTOPHER WILSON |
| Final | 6/28/2023 | Permit Finaled | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/28/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 6/28/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 6/28/2023 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 6/28/2023 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 6/28/2023 | Approved | CHRISTOPHER WILSON |