421 E VENICE WAY 90291

Certificate Information: 421 E VENICE WAY 90291

Application / Permit
19014-10002-06851
Plan Check / Job No.
B22WL03252
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
EPLAN Grading Permit for the major remodel/addition to (e) 1-story duplex with attached garage, resulting in a 3-story building with roof deck.k Grading work includes exavation under the building foot print (which covers under the builidng permit) and remove and recompact. This grading permit is for the remove and recompact of soil.
Permit Issued
Issued on 10/26/2022
Issuing Office
Metro
Current Status
Issued on 10/26/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/25/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 QUAN NGHIEM
Corrections Issued 10/4/2022 QUAN NGHIEM
Quality Review Completed 10/6/2022 CHAD DOI
Plan Check Approved 10/20/2022 QUAN NGHIEM
No Progress 10/20/2022 QUAN NGHIEM
Plan Check Approved 10/20/2022 QUAN NGHIEM
Issued 10/26/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/6/2022 ANTHONY MAINEZ
Work Adjacent to Public Way Cleared 10/6/2022 ANTHONY MAINEZ

Contact Information

Architect , ; Lic. No.: C34990 2347 OCEAN AVE      VENICE, CA 90291
Contractor Westside Construction; Lic. No.: 852976-B 1531 15TH STREET APT 6      SANTA MONICA, CA 90404

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/14/2023 Partial Approval MATTHEW JENKINS
Deputy Grading 5/5/2023 Conditional Approval MATTHEW JENKINS
Bottom/Toe 5/24/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 6/14/2023 Partial Approval MATTHEW JENKINS
Bottom/Toe 7/20/2023 Partial Approval AL GAMBLE
Bottom/Toe 11/17/2023 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 11/30/2023 Approved MATTHEW JENKINS
Approved Compaction Report 12/4/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 6/4/2024 Conditional Approval MATTHEW JENKINS
Bottom/Toe 8/1/2024 Partial Inspection MATTHEW JENKINS
Fill/Backfill 8/1/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 9/19/2024 Partial Approval MATTHEW JENKINS
Fill/Backfill 9/19/2024 Partial Inspection MATTHEW JENKINS
Approved Compaction Report 10/30/2024 Approved MATTHEW JENKINS