24 1/2 E DUDLEY AVE 90291

Certificate Information: 24 1/2 E DUDLEY AVE 90291

Application / Permit
19014-10002-01638
Plan Check / Job No.
B24LA07572
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN***SUPPLEMENTAL TO 19014-10000-01638. Revision work includes: Interior layout modifications Minor revisions to window and door sizes including additional replacement windows Additional replacement siding and sheathing as required by existing conditions. Revision to bedrrom layout on 2nd floor No change to building size, footprint, floor area or occupancy
Permit Issued
Issued on 9/30/2024
Issuing Office
Current Status
Permit Finaled on 9/4/2025

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 SINA KHOSRAVI
Corrections Issued 5/22/2024 SINA KHOSRAVI
Quality Review Completed 6/18/2024 CAROLYNN NEPOMUCENO
Plan Check Approved 8/23/2024 SINA KHOSRAVI
Issued 9/30/2024 APPLICANT
Permit Finaled 9/3/2025 JESUS RODRIGUEZ

Permit Application Clearance Information

Coastal Zone Cleared 8/8/2024 MATHEW QUAN
Specific Plan Cleared 8/8/2024 MATHEW QUAN
ZI Cleared 8/8/2024 MATHEW QUAN

Contact Information

Architect Ginter,, Gregory Hopkins; Lic. No.: NA30686       ,
Contractor Owner-Builder       ,
Engineer Trevellin,, Maurizio; Lic. No.: NA71368       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 10/30/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 10/30/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 10/31/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved HERBERT GIRON
HVAC-Rough 11/12/2024 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 11/12/2024 Partial Approval HERBERT GIRON
Shower Pan 11/12/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 12/4/2024 Corrections Issued HERBERT GIRON
Final 12/4/2024 Corrections Issued HERBERT GIRON
Green Building Rough 12/4/2024 Approved HERBERT GIRON
HVAC-Rough 12/4/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 12/4/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 12/12/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 12/12/2024 Approved HERBERT GIRON
Insulation 12/23/2024 Approved KENNETH NAGLE
Drywall Nailing 1/15/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/15/2025 Approved MICHAEL ALLEN
Final 6/10/2025 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 6/10/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 6/18/2025 Approved JESUS RODRIGUEZ
HVAC-Final 8/28/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 8/28/2025 Approved JESUS RODRIGUEZ
Final 9/3/2025 Permit Finaled JESUS RODRIGUEZ