1919 S VICTORIA AVE 90016
Certificate Information: 1919 S VICTORIA AVE 90016
- Application / Permit
- 19014-10001-07080
- Plan Check / Job No.
- B20LA16350
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO PERMIT NO. 19014 - 30000 - 07080 TO CHANGE MAIN ENTRANCE DOOR SIZE AND CORRECT HEIGHT IN STRUCTURAL INVENTORY. SEE COMMENTS
- Permit Issued
- Issued on 9/21/2020
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 9/21/2020 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/21/2020 | SERGIO GUTIERREZ |
| Issued | 9/21/2020 | APPLICANT |
| Permit Finaled | 11/23/2021 | STUART CHAPMAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/30/2020 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | STUART CHAPMAN |
| Reinforced Concrete Frame | 10/30/2020 | Approved | STUART CHAPMAN |
| Wood Frame | 11/23/2020 | Corrections Issued | STUART CHAPMAN |
| Insulation | 11/30/2020 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 2/17/2021 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 2/17/2021 | Corrections Issued | STUART CHAPMAN |
| Wood Frame | 2/17/2021 | Corrections Issued | STUART CHAPMAN |
| Pre-Inspection | 4/29/2021 | Corrections Issued | STUART CHAPMAN |
| Wood Frame | 4/29/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/3/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/3/2021 | Approved | STUART CHAPMAN |
| Pre-Inspection | 8/6/2021 | Not Ready for Inspection | ALFREDO BALANDRA |
| Final | 11/8/2021 | Corrections Issued | STUART CHAPMAN |
| METHANE-Final | 11/8/2021 | Approved | STUART CHAPMAN |
| Final | 11/15/2021 | Corrections Issued | LILIANA PORTILLO |
| Final | 11/23/2021 | Permit Finaled | STUART CHAPMAN |