6528 S 3RD AVE 90043
Certificate Information: 6528 S 3RD AVE 90043
- Application / Permit
- 19014-10001-06551
- Plan Check / Job No.
- B20LA21359
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO 19014-10000-06551 FOR THE FLOOR AREA REVISION TO APPROVED ADU. ALL WORK PER WOOD FRAME PRESCRIPTIVE DESIGN.
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | ZAW HAN |
| Corrections Issued | 12/8/2020 | ZAW HAN |
| Applicant returned to address corrections | 2/9/2021 | ADAM HEGAZI |
| Applicant returned to address corrections | 6/15/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 9/3/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 9/21/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 11/15/2021 | LUKE GONZALES |
| Plan Check Approved | 3/29/2022 | FARSHAD ALIMOHAMADI |
| Issued | 4/14/2022 | APPLICANT |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| Permit Finaled | 11/1/2022 | ENRIQUE MIRELES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/18/2020 | ROSA SILVA |
| Sewer availability | Cleared | 12/18/2020 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | ROSA SILVA |
| Construction near power lines | Cleared | 2/27/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/19/2022 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/22/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/17/2022 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 6/17/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 6/17/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/17/2022 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/21/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/2/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 8/16/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/16/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/19/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/22/2022 | Approved | ENRIQUE MIRELES |
| Final | 10/31/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 10/31/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 10/31/2022 | Approved | ENRIQUE MIRELES |