1965 1/2 E NEW JERSEY ST 90033
Certificate Information: 1965 1/2 E NEW JERSEY ST 90033
- Application / Permit
- 19014-10001-04619
- Plan Check / Job No.
- B21LA18985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 4/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2021 | CARLOS MONTES |
| Corrections Issued | 10/8/2021 | CARLOS MONTES |
| Quality Review Completed | 10/13/2021 | WING SUEN |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| Applicant returned to address corrections | 12/9/2021 | CARLOS MONTES |
| Plan Check Approved | 4/14/2022 | CARLOS MONTES |
| Issued | 4/14/2022 | APPLICANT |
| Permit Finaled | 3/13/2024 | FREDDIE RIVERA |
| Permit Finaled | 4/19/2024 | FREDDIE RIVERA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/13/2022 | VASIL MIHALEV |
| "Q" conditions | Cleared | 1/14/2022 | RYAN LY |
| Address approval | Cleared | 1/28/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 2/2/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 3/8/2022 | CHRIS VONG |
| GPI Written Notices | Cleared | 3/17/2022 | CARLOS MONTES |
| Roof/Waste drainage to street | Cleared | 3/19/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Soto,, Miguel Angel; Lic. No.: C87493 | 3756 MERCURY AVE LOS ANGELES, CA 90031 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 5/10/2022 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/12/2022 | Partial Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 5/13/2022 | No Result Entered | ROBERT VORHIS |
| Footing/Foundation/Slab | 8/25/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Partial Approval | FREDDIE RIVERA |
| Deputy Wood Construction | 11/10/2022 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/1/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/1/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/1/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 12/1/2022 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 12/1/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/1/2022 | Partial Approval | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 12/1/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/5/2022 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 12/5/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 12/5/2022 | Approved | FREDDIE RIVERA |
| Sewer | 12/5/2022 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 12/5/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | CALEB MEISTER |
| Insulation | 12/12/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 12/12/2022 | Approved | CALEB MEISTER |
| Shower Pan | 12/15/2022 | Approved | BRENDAN MORELLI |
| Drywall Nailing | 12/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/13/2024 | Permit Finaled | FREDDIE RIVERA |
| Green Building Final | 3/13/2024 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 3/13/2024 | Approved | FREDDIE RIVERA |
| Service/Power Release | 3/13/2024 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 3/13/2024 | Approved | FREDDIE RIVERA |